France,
Rhone-Alps
- fr/11
High Speed Railway
Closing Date:
25.04.2016 (Tender Closed)
Negotiated invitation to tender, deadline 25.04.2016, for environmental engineering consultancy services (except for the survey of Saint-Martin-la-Porte) on the French section of the international section of the new rail link Lyon-Turin. Time limit for receipt of requests for documents or for accessing documents is the 18.4.2016. Value of the contract is EUR4-7 millions, excluding VAT. The duration of the contract is 14 years. For further information contact Tunnel Euralpin Lyon Turin SAS, att.n Geraldine Decarre, Chambery, tel +33 479685679, fax +33 479685683, e-mail fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=107698-2016. 14/16.
The awarding procedure for environmental engineering consultancy services has been discontinued (except for the survey of Saint-Martin-la-Porte) on the French section of the international section of the new rail link Lyon to Turin. For further information contact Tunnel Euralpin Lyon Turin SAS, att.n Geraldine Decarre, Chambery, tel +33 479685679, fax +33 479685683, e-mail fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=116117-2016. 14/16
EGIS structures et environnement/Alpina SpA from Saint-Quentin-en-Yvelines secured the EUR 6 million contract for general management during construction of Avrieux shafts and underground work for the Villarodin-Bourget/Modane tunnel on the new Turin-Lyon high-speed railway. The shafts are for ventilation and safety for the future tunnel in Modane. Contact Tunnel Euralpin Lyon Turin SAS, attn Geraldine Decarre, Chambery, tel +33 479685679, fax +33 479685683, e-mail fonction.marches@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=307675-2016 and http://www.egis.fr. 36/16.
http://www.egis.fr/action/realisations/puits-davrieux-sur-la-nouvelle-ligne-ferroviaire-lyon-turin
Negotiated invitation to tender, deadline 09.11.2016, for environmental engineering consultancy services (except for the survey of Saint-Martin-la-Porte) on the French section of the international section of the new rail link from Lyon-Turin. Value of the contract is EUR3,927,000, excluding VAT. The duration of the contract is 72 months. Contact Tunnel Euralpin Lyon Turin SAS, att.n Geraldine Decarre, Chambery, tel +33 479685679, fax +33 479685683, e-mail fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=345744-2016. 41/16.
Negotiated invitation to tender, deadline 12.12.2016, for supply and delivery of electricity and related services for the Villarodin-Bourget/Modane tunnel on the new Turin-Lyon high-speed railway. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget-du-Lac, tel +33 479444240, fax +33 479685683, e-mail fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=401476-2016 and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=408719-2016. 47/16.
Negotiated invitation to tender, deadline 02.12.2016, for general management during the construction of the French section of the base tunnel of Moncenisio on new rail link Lyon-Turin. The bid is composed of three lots: 2 x 22 km in tunnel, duration 168 months, value EUR45 millions, excluding VAT (Lot 1); 2 x 24 km in tunnel, duration 168 months, value EUR45 millions, excluding VAT (Lot 2); 2 x 2,5 km in tunnel, duration 144 months, value EUR20 millions, excluding VAT (Lot 3). The contract includes the preparation of the tenders for the construction. For further information contact Tunnel Euralpin Lyon Turin SAS, att.n Geraldine Decarre, Le Bourget-du-Lac, tel +33 479685679, fax +33 479685683, e-mail fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=355503-2016. 41/16.
Negotiated invitation to tender, deadline 31.08.2017, for construction of Avrieux shafts and underground work for the Villarodin-Bourget/Modane tunnel for the new Turin-Lyon high-speed railway. The shafts are for ventilation and safety for the future tunnel in Modane. Value contract EUR300 million, excluding VAT. Duration contract 96 months. For further information http://fonction.contrats@telt-sas.com and contact Tunnel Euralpin Lyon Turin SAS, Le Bourget-du-Lac, tel +33 479444245, fax +33 479685683, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=235338-2017. 26/17.
Postponed to 02.10.2017 the deadline of the negotiated invitation to tender for construction of Avrieux shafts and underground work for the Villarodin-Bourget/Modane tunnel for the new Turin-Lyon high-speed railway. The shafts are for ventilation and safety for the future tunnel in Modane. Value contract EUR300 million, excluding VAT. Duration contract 96 months. For further information http://fonction.contrats@telt-sas.com and contact Tunnel Euralpin Lyon Turin SAS, Le Bourget-du-Lac, tel +33 479444245, fax +33 479685683, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=295499-2017 and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=357139-2017. 37/17.
Open invitation to tender for the following services:
Hardware maintenance and periodic support for TELT's IT infrastructure. Contact Tunnel Euralpin Lyon Turin SAS, Savoie Technolac, Bâtiment Homère, 13 allée
du Lac de Constance, CS 90281, Le Bourget Du Lac, 73375 either call on telephone:
+33 479685650 or e-mail: fonction.contrats@telt-sas.com.
Visit the main website www.telt-sas.com for further information click here http://ted.europa.eu/udl?uri=TED:NOTICE:452257-2017:TEXT:EN:HTML&src=0&tabId=0
. 46/17.
Open invitation to tender, deadline 30.11.2017, for
hardware maintenance and periodic support for TELT's IT infrastructure. Contact Tunnel Euralpin Lyon Turin SAS, Savoie Technolac, Bâtiment Homère, 13 allée
du Lac de Constance, CS 90281, Le Bourget Du Lac, 73375 either call on
telephone: +33 479685650 or e-mail: fonction.contrats@telt-sas.com.
Visit the main website www.telt-sas.com for further information click
http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=445624-2017
and
http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=452257-2017.
46/17.
Socotec from Chambery secured the EUR1.43 million, excluding
VAT, for environmental engineering consultancy services (except for the survey
of Saint-Martin-la-Porte) on the French section of the international section of
the new rail link from Lyon-Turin. Contact Tunnel Euralpin Lyon Turin SAS, Le
Bourget-du-Lac, tel +33 479685650, fax +33 479685683, e-mail fonction.contrats@telt-sas.com.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=002321-2018
and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=002334-2018
.02/18.
TELT secured to 13 European engineering companies for the
general management during the construction of the French section of the base
tunnel of Moncenisio on new rail link Lyon-Turin. Value contract EUR 90 million.
The contract is composed of three lots
including the tunnel between Italy-France border and the adit at
Villard-Clement in Saint-Julien-Montdenis municipality.
Lot 1: the JV ALLTI (Alliance Lyon Turin Ingenierie)
composed of Arcadis and BG Ingenieurs Conseils, Neosia (ex Tecnimont Civil
Construction), Lombardi Ingenierie and Amberg secured the 24 km section from
the Villerodin-Bouget/Modane survey gallery to be built by 2 TBMs. Duration
contract 10 years. Value EUR40 millions, excluding VAT.
Lot 2 : The JV Setec TPI (leader) with Systra, Italferr and
Pini Swiss Engineers secured the 21 km section between the La Praz and
Saint-Martin-la-Porte survey tunnels to be built by 3 TBMs. Duration contract
10 years. Value EUR37 millions, excluding VAT.
Lot 3 : the JV
Inalpage, composed of Egis (leader) with Ingerop, Alpina and Geodata secured
the 5 km section from Villard-Clement adit., to be built with NATM method.
Duration contract 4.5 years. Value EUR13.7 millions, excluding VAT.
Contact TELT sas, attn Geraldine Decarre, Le Bourget-du-Lac,
tel +33 479685679, fax +33 479685683, email fonction.contrats@telt-sas.com.
Visit http://www.telt-sas.com/it/contratti-direzione-lavori-francia/.
05/18.
Negotiated invitation to tender, deadline 23.03.2018, for the
assistance to the contracting authority and for studies during the construction
of the transborder section for the new Lyon-Turin rail link. Value of the
contract is EUR25 million, excuding VAT, for 168 months duration. Contact TELT sas, Le Bourget du Lac, email fonction.contrats@telt-sas.com.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=038092-2018
and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=038078-2018.
05/18.
Negotiated invitation to tender, deadline 28.05.2019, for
the construction of the base tunnel of the Lyon-Turin Railway Link Cross-border
Section from the French Side — Operational Worksites 5, 6/7 and 8. The contract
is composed of 3 lots.
• Lot 1,
Work site n.5 (base tunnel excavation from Villarodin-Bourget/Modane decline),
value EUR1bn, excluding VAT, duration 102 months;
• Lot 2,
Work site n.6/7 (base tunnel excavation from
La Praz and Saint-Martin-la-Porte declines), value EUR1.13bn, excluding
VAT, duration 98 months;
• Lot 3,
Work site n.8 (base tunnel excavation from Villard-Clement gates), value EUR180
million, excluding VAT, duration 98 months.
For further information https://telt.achatpublic.com/accueil/ where offers must be sent.
In accordance with article R.2185-1 of the Public
Procurement Code (former article 98 of Decree n. 2016-360), candidates and
bidders are reminded that the tender can be withdrawn, at any moment of the
procedure, up until the signing of the contract. In this case, bidders do not
have any right to sign the contract, or to be reimbursed for the expenses they
incurred as part of their application. The tender can be withdrawn by the
Contracting Entity because of economic, legal, or technical reasons, or following
a decision of the 2 States. Contact TELT sas, Le Bourget du Lac, tel +33
479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. For bid documents click here, here and here. Ref.n. T7. 11/19.
Additional information on the negotiated invitation to
tender, deadline 28.05.2019, for the construction of the base tunnel of the
Lyon-Turin Railway Link Cross-border Section from the French Side - Operational
Worksites 5, 6/7 and 8. The contract is composed of 3 lots:-
• Lot 1, Work site n.5 (base tunnel excavation from
Villarodin-Bourget/Modane decline), value EUR1bn, excluding VAT, duration 102
months;
• Lot 2, Work site n.6/7 (base tunnel excavation from La Praz and Saint-Martin-la-Porte declines),
value EUR1.13bn, excluding VAT, duration 98 months;
• Lot 3, Work site n.8 (base tunnel excavation from
Villard-Clement gates), value EUR180 million, excluding VAT, duration 98
months.
For further information https://telt.achatpublic.com/accueil/ where offers must be sent. Contact TELT sas,
Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. For bid documents click here and here. Ref.n. T7. 13/19.
The Consortium Artelia Ville & Transport (Choisy-le-Roi,
F), Tuc Rail (Bruxelles, B), Aecom (Madrid, E) and Geodes (Torino) secured the
contract for the assistance to the contracting authority and for studies during
the construction of the transborder section for the new Lyon-Turin rail link. Contact
TELT sas, Le Bourget du Lac, email fonction.contrats@telt-sas.com.
Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=341192-2019
and
http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=343446-2019.
Ref.n. C17306. 30/19.
Three contracts have been awarded for general management during the construction of the French section of the base tunnel of Moncenisio on the new Lyon-Turin rail link.
• The EEIG (European Economic Interest Grouping) ALLTI from Aix-les-Bains, composed of the following 9 companies Lombardi Ingegneria (Milan, IT), BG Ingenieurs Conseils SA (Losanna, CH), Lombardi SA Ingenieurs-Conseils (Minusio, CH), Tecnimont civil construction SPA (Milan, IT), BG Ingenieurs conseils SAS (Ivry-sur-Seine, FR), Amberg infrastructures (Las Rosas, Madrid, ES), Arcadis (Villeurbanne, FR), Amberg Engineering SA (Regensdorf-Watt, CH), Lombardi Ingenierie Lyon (Lyon, FR) secured Lot 1 (general management during underground work from Villarodin-Bourget/Modane
adit);
• Setec TPI mandatory of the Joint Venture Setec (Paris, FR)/ Systra (Paris, FR), Italferr (Rome, IT), Pini Swiss Engineers (Lugano, CH) secured Lot 2 (general management during underground work from Saint-Martin-la-Porte and La Praz, excluding ongoing reconnaissance works);
• Egis structures & Environment, mandatory of the Joint Venture Egis structures & environment (Saint-Quentin-en-Yvelines, FR), Ingerop (Reuil-Malmaison, FR), Alpina (Milan, IT), Geodata Engineering (Turin, IT) secured Lot 3 (general management during underground work from
Villard-Clement portals). Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget-du-Lac, email
fonction.contrats@telt-sas.com. For bid documents click here. 39/19.
Open invitation to tender, deadline 08/10/2019, for maintenance of TELT’s telepresence system for the new Lyon-Turin railway link project. Duration of the contract is 36 months. For bid documents
https://telt.achatpublic.com/accueil/ where offers must be sent. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email Fonction.contrats@telt-sas.com. For bid documents click here and here. Ref. Maint_TP. 39/19.
Open invitation to tender, deadline 11/12/2019, for the audit of the information systems of TELT. Value contract EUR50,000, excluding VAT.
Duration of the contract is 6 months. For bid documents https://telt.achatpublic.com/accueil/ where offers must be sent. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, email fonction.contrats@telt-sas.com. For further tender information please click here .
47/19.
Connect SpA from Pianezza (TO) secured the EUR82,266 contract, excluding VAT, for maintenance of TELT’s telepresence system for the new Lyon-Turin railway link project. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email Fonction.contrats@telt-sas.com. For tender documents please click here . Ref. Maint_TP. 04/20.
Connect SPA from Pianezza (TO) secured the EUR82,266.03 contract, excluding VAT, for maintenance of TELT’s telepresence system for the new Lyon-Turin railway link project. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email Fonction.contrats@telt-sas.com. For tender documents please click here. Ref. Maint_TP. 05/20.
Open invitation to tender, deadline 09/07/2020, for assistance to the General Management for economic and socio-economic studies of the cross-border section of the Lyon-Turin railway line. Value of the contract is EUR412,000, excluding VAT. Duration of the contract is 12 months. For bid documents https://telt.achatpublic.com/accueil/ where tenders have to be sent. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel. +33 479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. For tender information please click here 22/20.
The contract for TELT functional, organizational and technical audit services was not awarded Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, email fonction.contrats@telt-sas.com. For further tender documents please click here. Ref. S47. 02/21.
The JV ALLTI (Alliance Lyon Turin Ingénierie) GEIE from Aix-les-Bains, Arcadis ESG from Paris, Lombardi Ingenierie from Lyon, Neosia SPA from Milan, BG Ingenieurs Conseils from Ivry-sur-Seine and Amberg Infraestructuras SA from Madrid secured the EUR 19.24 million contract, excluding VAT, for project management service for management and use of excavated materials on the French side of the cross-border section of the Lyon-Turin railway line. Duration contract 168 months. Contact TELT SAS, Le Bourget du Lac, email fonction.contrats@telt-sas.com. For further on the tender, please click here. Ref. S37. 02/21.
The three lots for the French section of the base tunnel of the international section of the new rail link Lyon to Turin have been awarded.
The consortium Eiffage Genie Civil (group head) /Spie Batignolles/Ghella/Cogeis secured the EUR1.47 bn contract for the construction of the 22 km stretch of tunnel between the existing Villarodin-Bourget/Modane tunnel and Italy (Lot 1). Duration of the contract will be 72 months. Two TBMs will be used towards Turin and the traditional method of tunnelling will be used towards Lyon. The Modane safety site, the communication branches located every 333 m between the two tunnels, necessary for maintenance and safety, and all the niches and transverse tunnels for operation and safety, will also be done in this phase. Visit https://www.eiffagegeniecivil.com/.
The consortium Vinci Construction Grands Projets (group head) / Dodin Campenon Bernard/Vinci Construction France TP Lyon /WeBuild secured the EUR1.43 bn contract for the construction of the 23 km section of tunnel between Saint-Martin-la-Porte/La Praz and Modane (Lot 2). Excavation continues along the 10-km-long section, already completed at Saint-Martin-la-Porte, towards Italy. All 23 km of the twin-tube between Saint-Martin-la-Porte, La Prazand Modane will be excavated. Duration of the contract is 65 months. Three TBMs will be used , while the more geologically complex sections will be excavated using traditional methods. The territories of the municipalities of Saint-Martin-la-Porte, Saint-Michel-de-Maurienne, Orelle, Saint André, Villargondran and Saint-Julien-Mont-Denis will be involved. The La Praz safety site, communication branches every 333 m between tunnels, technical rooms, niches and tunnels for operation and safety will also to be built in this lot. Visit https://www.vinci.com and https://www.webuildgroup.com/en/.
The consortium Implenia Suisse (group head) / Implenia France / NGE / itinera / Rizzani de Eccher secured the EUR228 million contract for the construction of the 3 km tunnel section between the French entrance portal at Saint-Julien-Montdenis and Saint-Martin-la-Porte (Lot 3). Excavation in this section will be carried out using the traditional method. There are also works planned on the Villard-Clément platform between the artificial tunnel to the west (the cut and cover tunnel, already built) and the natural entrance of the tunnel into the mountain to the east. In addition, there will be communication branches every 333 metres between the two tunnels, technical rooms and niches for operation and safety. Duration of the contract is 70 months. Visit https://implenia.com/.
For further information, please click here and visit https://www.telt-sas.com/en. 27/21.
The contracts for the construction of the base tunnel of the Lyon-Turin Railway Link Cross-border Section from the French Side - Operational Worksites 5, 6/7 and 8, have been awarded:
- the Joint Venture Eiffage Génie Civil from Vélizy-Villacoublay, Spie Batignolles from Nanterre, Ghella from Rome and Cogeis from Quincinetto secured the EUR1.61 billion contract, excluding VAT, for Lot 1, Work site n.5 (base tunnel excavation from Villarodin-Bourget/Modane decline);
- the Joint Venture Vinci Construction Grands Projets from Rueil-Malmaison, Dodin Campenon Bernard from Toulouse, Vinci Construction France TP Lyon from Villeurbanne and WeBuild from Milan secured the EUR1.66 bn contract, excluding VAT, for Lot 2, Work site n.6/7 (base tunnel excavation from La Praz and Saint-Martin-la-Porte declines);
- the Joint Venture Implenia Suisse from Dietlikon, Implenia France from Archamps, NGE from Tarascon, Itinera from Tortona and Rizzani de Echer from Pozzuolo del Friuli secured the EUR304.83 million contract, excluding VAT, for Lot 3, Work site n.8 (base tunnel excavation from Villard-Clement gates).
Contact TELT sas, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=517558-2021 (French), http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=517557-2021 (Italian) and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=517556-2021 (English). Ref.n. T7. 41/21.
The Joint Venture EIFFAGE GC INFRA LINEAIRES - ETS FOREZIENNE / EIFFAGE ROUTE CENTRE EST / EIFFAGE GENIE CIVIL - ETS RESIREP SAINT-ETIENNE from Montmelian, EIFFAGE ROUTE CENTRE EST from La Motte Servolex and EIFFAGE GENIE CIVIL - ETS RESIREP ST ETIENNE from SORBIERS secured the EUR1.18 million contract, excluding VAT, for the site road (Lot 1) to be used as a Modane bypass by the trucks involved in the new Lyon-Turin base tunnel construction, site n.5 Villarodin-Bourget/Modane. Contact TELT sas, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email
fonction.contrats@telt-sas.com. Visit
http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=459558-2021. Ref.n. T10. 37/21
Open invitation to tender, deadline 20/06/2022, for updating of the LTF2004 geodesic system and the reference points’ coordinates of the operational sites on the new Turin-Lyon railway line. For tender documents please click here, where tenders must be sent. Value of the contract is EUR 430,500 excluding VAT. Duration of the contract will be 12 months. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=245745-2022. Ref. n. MS70 - C210348. 20/22.
France-Le Bourget-du-Lac: Topographical services
2022/S 089-245745
Contract notice – utilities
Legal Basis:
Directive 2014/25/EU
Section I: Contracting entity
I.1)Name and addresses
Official name: Tunnel Euralpin Lyon Turin SAS
Postal address: Savoie Technolac - Bâtiment Homère - 13 allée du Lac de Constance - BP 281
Town: Le Bourget du Lac
NUTS code:
FRK27 Savoie
Postal code: 73375
Country: France
Contact person: Direction Achats
E-mail:
fonction.contrats@telt-sas.com
Telephone: +33 479685650
Fax: +33 479685683
Internet address(es):
Main address:
www.telt-sas.com
Address of the buyer profile:
https://telt.achatpublic.com/accueil/
I.6)Main activity
Railway services
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
ACTUALISATION DU SYSTEME GEODESIQUE LTF2004 ET MISE A JOUR DES COORDONNEES DES POINTS DE REFERENCE DES CHANTIERS OPERATIONNELS
Reference number: MS70 - C210348
II.1.2)Main CPV code
71351810 Topographical services
II.1.3)Type of contract
Services
II.1.5)Estimated total value
Value excluding VAT: 430 500.00 EUR
II.1.6)Information about lots
This contract is divided into lots: no
II.2)Description
II.2.2)Additional CPV code(s)
71356300 Technical support services
II.2.3)Place of performance
NUTS code: FRK27 Savoie
NUTS code: ITC1 Piemonte
II.2.6)Estimated value
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 12
This contract is subject to renewal: no
Section IV: Procedure
IV.2)Administrative information
IV.2.2)Time limit for receipt of tenders or requests to participate
Date: 20/06/2022
Local time: 13:00
IV.2.3)Estimated date of dispatch of invitations to tender or to participate to selected candidates
IV.2.4)Languages in which tenders or requests to participate may be submitted:
French, Italian
Section VI: Complementary information
VI.5)Date of dispatch of this notice:
03/05/2022
France-Le Bourget du Lac: Infrastructure works consultancy services
Notice for changes or additional information
Legal Basis:
Directive 2014/25/EU
Section I: Contracting authority/entity
I.1)Name and addresses
Official name: Tunnel Euralpin Lyon Turin SAS
Postal address: Savoie Technolac - Bâtiment Homère - 13 allée du Lac de Constance - BP 281
Town: Le Bourget du Lac
NUTS code: FRK27 Savoie
Postal code: 73375
Country: France
Contact person: Fonction contrats de projet France
E-mail:
fonction.contrats@telt-sas.com
Telephone: +33 479685650
Fax: +33 479685683
Internet address(es):
Main address:
www.telt-sas.com
Address of the buyer profile:
https://telt.achatpublic.com/accueil/
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Missions d'Assistance à maîtrise d'ouvrage (AMO) pour la rédaction des documents de la consultation (DC) du marché public de "Gestionnaire d'infrastructure virtuelle" pour TELT
Reference number: MS81
II.1.2)Main CPV code
71311300 Infrastructure works consultancy services
II.1.3)Type of contract
Services
Section VI: Complementary information
VI.6)Original notice reference
Section VII: Changes
VII.1)Information to be changed or added
VII.1.2)Text to be corrected in the original notice
Section number: IV.2.2
Instead of:
Date: 01/07/2022
Local time: 13:00
Read:
Date: 08/07/2022
Local time: 13:00
Section number: IV.2.7
Instead of:
Date: 01/07/2022
Local time: 15:00
Read:
Date: 08/07/2022
Local time: 15:00
VII.2)Other additional information:
Negotiated invitation to tender, deadline 07/12/2022, for the treatment and manipulation of inert and sulphated materials coming from the excavation of the base tunnel of the new Turin-Lyon railway link project. For tender documents please click here, where tenders must be sent. Value of the contract - composed by 2 lots - is EUR25.50 million, excluding VAT. Duration of the contract will be 120 months. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=560672-2022. Ref. n. T21. 44/22.
France-Le Bourget-du-Lac: Excavating and earthmoving work
Contract notice – utilities
Legal Basis:
Directive 2014/25/EU
Section I: Contracting entity
I.1)Name and addresses
Official name: Tunnel Euralpin Lyon Turin SAS
Postal address: Savoie Technolac - Bâtiment Homère - 13 allée du Lac de Constance - BP281
Town: Le Bourget du Lac
NUTS code: FRK27 Savoie
Postal code: 73375
Country: France
Contact person: Fonction Contrats de Projets France
E-mail:
fonction.contrats@telt-sas.com
Internet address(es):
Main address:
www.telt-sas.com
Address of the buyer profile:
https://telt.achatpublic.com/accueil/
I.6)Main activity
Railway services
Section II: Object
II.1)Scope of the procurement
II.1.1)Title:
Accueil et travaux de valorisation de matériaux inertes et sulfatés issus du creusement du tunnel de base du projet de nouvelle liaison ferroviaire Lyon-Turin
Reference number: T21
II.1.2)Main CPV code
45112000 Excavating and earthmoving work
II.1.3)Type of contract
Works
II.1.5)Estimated total value
II.1.6)Information about lots
This contract is divided into lots: yes
II.2)Description
II.2.1)Title:
Accueil et valorisation de matériaux inertes issus de l’excavation (hors matériaux sulfatés), acheminés par voie routière
Lot No: 1
II.2.2)Additional CPV code(s)
45112000 Excavating and earthmoving work
90000000 Sewage, refuse, cleaning and environmental services
II.2.3)Place of performance
NUTS code: FRK27 Savoie
II.2.6)Estimated value
Value excluding VAT: 13 860 000.00 EUR
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 120
This contract is subject to renewal: no
II.2)Description
II.2.1)Title:
Accueil et valorisation de matériaux inertes issus de l’excavation (hors matériaux sulfatés), acheminés par voie ferroviaire
Lot No: 2
II.2.2)Additional CPV code(s)
45112000 Excavating and earthmoving work
90000000 Sewage, refuse, cleaning and environmental services
II.2.3)Place of performance
NUTS code: FRK27 Savoie
II.2.6)Estimated value
Value excluding VAT: 11 640 000.00 EUR
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 120
This contract is subject to renewal: no
II.2)Description
II.2.1)Title:
Accueil et valorisation de matériaux sulfatés issus de l'excavation, acheminés par voie routière
Lot No: 3
II.2.2)Additional CPV code(s)
45112000 Excavating and earthmoving work
90000000 Sewage, refuse, cleaning and environmental services
II.2.3)Place of performance
NUTS code: FRK27 Savoie
II.2.6)Estimated value
Value excluding VAT: 7 590 000.00 EUR
II.2.7)Duration of the contract, framework agreement or dynamic purchasing system
Duration in months: 120
This contract is subject to renewal: no
Section IV: Procedure
IV.2)Administrative information
IV.2.2)Time limit for receipt of tenders or requests to participate
Date: 07/12/2022
Local time: 14:00
IV.2.3)Estimated date of dispatch of invitations to tender or to participate to selected candidates
IV.2.4)Languages in which tenders or requests to participate may be submitted:
French
Section VI: Complementary information
VI.5)Date of dispatch of this notice:
07/10/2022
Open invitation to tender, deadline 14/11/2022, for the project management assistance services (AMO) in the field of public procurement under French law for the new Turin-Lyon railway link project. For tender documents please click here, where tenders must be sent. Duration of the contract will be 48 months. Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, tel +33 479685650, fax +33 479685683, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=560850-2022. Ref. n. MS86. 44/22.
Open invitation to tender, deadline 04/05/2023, for topographic services of the new Lyon-Turin base tunnel, on the French side. For tender documents please click here, where tenders must be sent. Value of the contract is EUR421,000 excluding VAT. Duration of the contract will be 12 months. Contact Tunnel Euralpin Lyon Turin SAS, Chambery, tel +33 479685650, email fonction.contrats@telt-sas.com. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=225981-2023, http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=225687-2023, http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=185745-2023 and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=184178-2023. Ref.n. MS72. 16/23.
The Joint Venture GEME composed of the French companies EUROVIA Alpes / Carrieres du Bassin Rhonalpin / SATM / Granulats VICAT / SPIE BATIGNOLLES VALERIAN / SPIE BATIGNOLLES MALET / VINCI Construction Terrassements / GIE GMM 73 have secured the EUR799.7 million contract for the recovery of excavation materials on the French side of the Mont Cenis base tunnel. With a view to sustainable development and circular economy. TELT has chosen to aim for maximum reuse of materials extracted during civil works. It is estimated that of the 37 million tons of these excavated earth and rocks, of which approximately 30 million tons extracted in France, over 50% will be reused in the works. A reuse objective that could reach 60% thanks to the recent agreement signed by the Intergovernmental Commission on behalf of the Italian and French governments. For the first time in Europe, in fact, it becomes possible to reuse excavation materials beyond national borders, considering the international section of the Turin-Lyon as a "single construction site".
Depending on their characteristics, materials have different uses and destinations. In particular, a part will be treated in two valorization sites (one near Saint-Jean-de-Maurienne and the other in Modane) where these rocks will be processed to create the concrete to be reused on the base tunnel construction sites. Another part will be used on the construction site of the new tracks in the Saint-Jean-de-Maurienne basin, where the railway embankments will be built.
Finally, the materials that cannot be reused in the international section of the new line will still be directed towards authorized storage sites or former quarries to be restored.
Contact Tunnel Euralpin Lyon Turin SAS, Le Bourget du Lac, email fonction.contrats@telt-sas.com. Visit https://www.telt.eu/ and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=781596-2023. 40/23.