Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Archive - News

Featured News

Production of segments completed in Ahrental for the Austrian H41 construction site of the Brenner Base Tunnel

Production of segments completed in Ahrental for the Austrian H41 construction site of the Brenner Base Tunnel

On Saturday 19 July, production of the precast concrete segments used by the TBMs for the final lining of the line tunnels were completed at the Ahrental plant located  near the Austrian H41 ... More Information

A new breakthrough in one of the two main tunnels on the Austrian side of the project

A new milestone in the BBT project, on May 20th , a break through was made in the western main tunnel between the two lots H41 Sill Gorge-Pfons and H21 Sill Gorge.  In the western main tunnel ... More Information

Pfons-Brenner construction lot: Breakthrough in the east main tunnel

A new milestone has been reached for the H53 Pfons-Brenner construction lot in the Austrian part of the BBT project, in the geologically challenging area of Hochstegen. On the 08/05/2025 a ... More Information

BBT - TBM Excavation Completed on the Italian Side

BBT - TBM Excavation Completed on the Italian Side

Flavia, the last Italian TBM for the BBT project, has reached the Brenner Pass, completing the excavation of the west main tunnel in lot H61 Mules. This marks the end of mechanized excavation on the ... More Information

TBM Lilia Crosses Werner Fault Zone, Reaches 6 km Milestone on BBT Project

Tunnel boring machine (TBM) Lilia has reached a major milestone in the construction of the Brenner Base Tunnel (BBT), having successfully crossed the Werner fault zone and completed 6 kilometers of ... More Information

First kilometre for Wilma, the Austrian TBM advancing north

First kilometre for Wilma, the Austrian TBM advancing north

While Flavia is only 300 m from its final destination and Ida has already passed the Werner fault zone, the TBM Wilma reached its first kilometre of excavation at 10:40 on Sunday 2 March after ... More Information

BBT - TBM Flavia is getting closer to its goal

The TBM Flavia, length 200 m and weight 2750 t - launched in April 2019 – which has advanced with a driving power of 4200 kW under a rock cover of over 1200 m. The TBM has now completed the ... More Information

TBM Breakthrough for the parallel Thimble Shoal Tunnel

TBM Breakthrough for the parallel Thimble Shoal Tunnel

The Parallel Thimble Shoal Tunnel Project at the Chesapeake Bay Bridge-Tunnel reached a significant milestone on Monday, January 27, 2025 when the Herrenknecht TBM Chessie - measuring 13.26 m (43.5 ... More Information

BBT - New milestones for TBM Ida

BBT - New milestones for TBM Ida

Since May and June of 2023, the two TBMs Lilia and Ida have been working southwards on the Austrian H41 Sill Gorge-Pfons construction site of the BBT project. The excavation work is being ... More Information

North portal completed for BBT

North portal completed for BBT

As of December 2024, the Sill Gorge construction lot, which houses the north portal of the Brenner Base Tunnel, is officially completed.  There are already numerous infrastructures in the ... More Information

Final Stretch of TBM Flavia’s Journey: Last Kilometre of Excavation in the Western Main Tunnel

TBM Flavia, a colossal tunnel boring machine measuring 200 meters in length, weighing 2,750 tons, and powered by 4,200 kW, is nearing the completion of its excavation journey. Launched in April 2019 ... More Information

BBT - First breakthrough in the main Brenner Base tunnel in Austrian area

The ceremony has been held for the last breakthrough of the first main tunnel in the Austrian territory of the Brenner Base Tunnel. The breakthrough is at the Sill Gorge site, between lots H21 Sill ... More Information

BBT - Launch of the Wilma and Olga TBMs

The launch of the Wilma and Olga TBMs will take place on Wednesday 18th  September 2024 at the BBT H53 Pfons-Brenner construction site.  The first components of the two TBMs - after ... More Information

TBM Ida completes 4 Km of the westbound tube of the Brenner Base Tunnel, H41 Lot

On 22 July, the TBM Ida celebrated the excavation of the first 4 km - out of its total 8.4 km - of the westbound line tunnel to the south at the Austrian H41 Sill-Pfons Gorge construction site. The ... More Information

June updates for BBT

Press Release - H53 Pfons-Brenner construction site: the first segments reach the construction site The two TBMs Wilma and Olga - which from September 2024 will dig and line the twin tube 7.5km ... More Information

Italy/Trentino-South Tyrol – Work has started on the southern entrance to the Trento railway bypass

Work continues on the construction of 13 km (Lot 3A) of the new railway line - almost entirely underground – linking to the future Brenner Base Tunnel. The new infrastructure will begin from ... More Information

Brenner Base Tunnel update

Brenner Base Tunnel update

Every year BBT organises an Open Day for the Brenner Base Tunnel project. They take place at the Austrian construction site H41 Sill-Pfons Gorge, and at the construction site of the Eisack ... More Information

BBT - TBM Ida reaches first 3 km of excavation for Lot H41 Sill-Pfons Gorge

On 14 May 2024  the TBM Ida, launched back in June 2023, reached its first 3 km of excavation towards the south, in the West line tunnel, advancing an average of 13 m/day and extracting ... More Information

TBM Wilma is ready for the Brenner Base Tunnel

TBM Wilma is ready for the Brenner Base Tunnel

On 8 march 2024 BBT SE and H53 Consortium consisting of Porr Bau GmbH, Marti GmbH Austria and Marti Tunnel AG Switzerland completed the factory acceptance of Wilma. This will be the first of the two ... More Information

BBT - New milestone for the TBM Ida on the H41 Sill-Pfons Gorge construction site

The TBM Ida in the H41 Sill-Pfons Gorge lot of the Brenner Base Tunnel is continuing its journey through the westbound line tunnel in a southerly direction.  On Sunday, 25 February 2024, ... More Information

BBT - Take part in choosing the names of the two new TBMs for the Brenner Base Tunnel

Until 12 noon today, 22 February, you can participate in the choice of names for the two 160 m long TBMs that will come into operation in autumn 2024 for the excavation of the Austrian Pfons-Brenner ... More Information

Scaleres tunnel’s TBM assembled

In the ongoing construction of the Scaleres tunnel's the Tunnel Boring Machine (TBM) on the Fortezza-Verona line in Italy, SELI Overseas, a specialized subcontractor for the Munich-Verona railway ... More Information

BBT - Updates on the Brenner Base Tunnel

Hochstegen: Another construction lot of the Brenner Base Tunnel is now complete  The Swietelsky Tunnelbau company, which in 2021 secured the EUR102 million contract for the construction ... More Information

BBT - Eisack Underpass work completed

All the main works have been completed at the construction site of lot H71 “Eisack River underpass” of the Brenner Base Tunnel, and subsequently the work completion report has now been ... More Information

BBT - TBM Virginia has reached the border with Austria

On 28/03/2023 an important milestone was reached for the Brenner Base Tunnel, on the Italian side, at the Mules (BZ) construction site.  After 14 km of excavation and almost 4 years of ... More Information

TBM Ida will drive the west main Brenner Base Tunnel

On the 14/02/2023 the official inspection of the second TBM for the H41 Sill Gorge-Pfons construction lot of the Brenner Base Tunnel took place at Herrenknecht AG in Schwanau (D). The ... More Information

BBT - Segments production started for lot H41 Sill Gorge-Pfons

The main part of tunnels in lot H41 Gola del Sill-Pfons will be driven by two TBMs. The machines - during their tunnelling - will install the rings, composed of prefabricated concrete ... More Information

TBM Lilia for Brenner Base Tunnel passes acceptance test

TBM Lilia for Brenner Base Tunnel passes acceptance test

The first of the two TBMs for the H41 Sill Gorge-Pfons construction lot of the Brenner Base Tunnel has formally passed its acceptance test at Herrenknecht AG in Schwanau, Germany. The ... More Information

SAIE 2022 - The SIG (Società Italiana Gallerie) tunnelling area

SAIE 2022 - The SIG (Società Italiana Gallerie) tunnelling area

Press release - Among the various special initiatives that uniquely characterize the SAIE 2022, the Construction, Design, Building and Plants’ Fair - in BolognaFiere from 19 to 22 October, ... More Information

BBT - excavations begin for lot H41 Sill Gorge-Pfons

BBT -  excavations begin for lot H41 Sill Gorge-Pfons

Excavation work has begun on the main tunnel for BBT construction lot H41 Sill Gorge-Pfons, in Ahrental near Innsbruck. The Austrian Federal Minister Leonore Gewessler the patroness was ... More Information

BBT – Breakthrough in the Brenner Base Tunnel

BBT – Breakthrough in the Brenner Base Tunnel

On the 19/05/2022 at 13h45 an excavator broke through between lot H71 Eisack undercrossing (built by Webuild) and Lot Mules 2-3 (built by Webuild and Ghella), on the Italian side of the East line ... More Information

BBT – Excavation has started at the H52-Hochstegen construction lot in Austria

On 04/05/2022 a ground breaking ceremony was held for Lot H52 Hochstegen in the presence of Maria Lorenzatto, godmother of the tunnel, along with the various authorities and companies involved. The ... More Information

BBT - Breakthrough under Isarco river

BBT - Breakthrough under Isarco river

On 07/04/2022 about a month after the start of the excavation work, the last main tunnel below the Eisack riverbed for the future railway Brenner Base Tunnel has broken through.   A total ... More Information

Progress report for the Brenner Base Tunnel

As of January 2022, 4 main construction lots are under construction: Mules 2-3, Isarco River Underpass (Italian project area); Sill gorge, Sill gorge - Pfons (Austrian project area).  In ... More Information

BBT - Exploratory tunnel excavation completed

On the 24/11/2021 TBM Serena with a diameter of 6.85m, a length of approximately 300m and weight 1,500 t has reached the Brenner Pass. The TBM has excavated over 14 km of tunnel in 3.5 years. The ... More Information

Brenner Base Tunnel - Update of Total Project Costs

On the 07/09/2021, after the approval of the updated construction programme, approval was also obtained for the total costs of the BBT project, which had been updated to take the following issues ... More Information

Page:

Tunnelling News

Kerala Moves Closer To Vizhinjam–Balaramapuram Tunnel Rail Project

The Kerala government is preparing to invite bids next month for the tunnel rail project linking Vizhinjam International Seaport with ... More Information

Norway's Ship Tunnel Project Under Threat as Costs Rise

New cost estimates suggest the ambitious project will far exceed its approved budget, raising questions about whether it will ever be built. More Information

Davao City Bypass southbound tunnel nears breakthrough

The Department of Public Works and Highways (DPWH) announced that the southbound tunnel of the Davao City Bypass Construction Project (DCBCP) is ... More Information

CA should pursue better alternatives to the costly Delta Tunnel Project Stocktonia

Governor Gavin Newsom is attempting to fast-track the construction of a massive, budget-busting water tunnel through the Delta to ship freshwater to ... More Information

Physical Origins of Shear Strength Fluctuations in Fault Gouges

Fault gouge is rock texture within fault zones that may include rock fragments (RF) and foliated structures. Previous studies have primarily focused on remould soils, the natural structure ... More Information

Webuild expands its role in high-speed rail projects

Four modern tunnel boring machines will be deployed to ensure precision and safety in complex geological conditions. Once completed, the old single- ... More Information

Hudson Tunnel Project advances as tunnel boring machines near completion

The Hudson Tunnel Project hit a key milestone as massive tunnel boring machines near completion, with delivery set for November. More Information

Nagdhunga tunnel in final stages of construction

If we look at the history of road construction and development in Nepal, there are various records of road construction starting from the Rana period. According to articles published in ... More Information

Boring of tunnel across Yellow River completed in China's Shandong

Constructed by using a "Shanhe" shield machine with a 17.5-meter excavation diameter, this double-deck, two-way, six-lane tunnel stands as the world's ... More Information

The £1.6bn plan for world's deepest underwater road tunnel leaving 'no room for error'

Opening of Rogfast tunnel under construction. The Rogfast tunnel will be the longest and deepest undersea road tunnel on Earth. (Image: SKANSA). A ... More Information

Tunnelling complete on NSW's Coffs Harbour bypass project

Tunnelling has been completed on the A$2.2bn (£1.1bn) Coffs Harbour bypass project in New South Wales, Australia, with the excavation of the third ... More Information

Veidekke acquires tunnel construction contract for Gothenburg's West Link Project

Veidekke has received a contract from the Swedish Transport Administration to build the Stora Hamnkanalen tunnel, a component of the West Link ... More Information

German Rail completes construction of Rastatt Tunnel

GERMAN Rail (DB) has completed civil works on the new 4270m twin-bore Rastatt Tunnel, a major component of the project to widen to four tracks the ... More Information

Final contracts signed for Eastern Freeway transformation

A huge amount of work is underway to build North East Link and upgrade the freeways – two tunnel boring machines are digging deep under Rosanna ... More Information

Progress on Sydney pipeline duplication

Bouygues Construction Australia and Rob Carr have launched a tunnel boring machine (TBM) on Sydney Water's Thornleigh pipeline duplication ... More Information

The latest plan to connect BART to downtown San Jose: One tunnel rather than two

When BART and Santa Clara Valley Transportation Authority first discussed plans to send trains rolling under downtown San Jose, transit officials contemplated a design with two tunnels ... More Information

Nashville Tesla tunnel: Here's when construction could start on the Music City Loop

Elon Musk's The Boring Company is currently in the design phase of constructing a tunnel connecting downtown Nashville to the Nashville ... More Information

World's longest underwater 'mega tunnel' to cost $46 billion but will halve 21-hour drive

Oddvar Kaarmo, the Rogfast project manager, cited additional motivation for the tunnel's construction: "The port at Mortavika is quite exposed and ... More Information

China's first vertical large model for tunnel, underground space sector released

The project which is in the Guangdong-Hong Kong-Macao Greater Bay Area. The model helps make tunnel construction safer, higher-quality, more efficient and ... More Information

BMC Begins Major Water Supply Upgrade Mumbai

The project commenced in 2023 and has adopted tunnel boring machine (TBM) technology to minimise surface disruptions in crowded neighbourhoods. Of ... More Information

Slurry tunnel boring machines to be deployed for Bengaluru Twin Tunnel Road Project

B-SMILE opts for slurry TBMs over hard rock TBMs for Twin Tunnel Road project in Bengaluru due to mixed terrain... More Information

Tunnel along railway linking Shenzhen and Shanwei special cooperation zone under construction

Technicians check a tunnel boring machine (TBM) at the construction site of a tunnel in Pingshan, Shenzhen City, south China's Guangdong Province, Aug ... More Information

Construction staging area approved for Nashville's airport tunnel project

The Music City Loop will be a 10 mile tunnel connecting downtown Nashville to the Nashville International Airport (BNA)... More Information

Zojila tunnel deadline pushed to 2028: Here's why Asia's longest tunnel project is delayed

Zojila Tunnel Latest Update: On completion, the project will not only play an important role in the country's infrastructure development but also ... More Information

W.A. Rasic Construction Awarded Major Subcontract on Dragados' $630M Effluent Outfall

The tunnel project is a critical component of Southern California's long-term infrastructure resilience strategy. The project directly supports the ... More Information

VDOT gives HRBT expansion update

Construction on the Hampton Roads Bridge-Tunnel Expansion Project hit key milestones as tunneling progresses and traffic shifts to new lanes. More Information

HS2 lifts third TBM following 3.4-mile journey

HS2 Ltd has lifted Tunnel Boring Machine Emily's 9.11-metre diameter cutterhead, front and middle shield, weighing 880 tonnes, from below the ... More Information

Musk's Boring Company unveils Music City Loop tunnel project for Nashville

The big picture: The project has an ambitious timeline of completing the 10-mile route in less than two years. The tunnel would move vehicles at warp ... More Information

Progress Update on East Dallas Tunnel Project to Address Flooding Problems

With so much rainfall throughout the metroplex, NBC 5 wanted an update on a project expected to mitigate flooding in East Dallas... More Information

KIB gets go-ahead for landmark Kuwait tunnel revamp project

On the key tunnel beautification project, Vice Chairman and CEO Raed Jawad Bukhamseen said: "This initiative reflects KIB's vision of supporting ... More Information

From hills to hope

As night falls over the northern highlands of Lesotho in early July, winter's chill sets in. Yet, the Polihali Transfer Tunnel construction site ... More Information

Tunnel boring machines reach Parramatta in major Metro West milestone

Tunnel boring machines have reached Parramatta, marking a major milestone in the construction of the Metro West project. More Information

Completion of hyperbaric excavated tunnel marks major milestone for Naples-Bari rail project

The construction of the Casalnuovo Tunnel, a critical and technically challenging segment of the high-speed railway line between Naples and Bari ... More Information

Multraship tugs support Antwerp Scheldt tunnel construction

Tugboats are supporting the construction of a motorway tunnel in the River Scheldt in Antwerp by towing and manoeuvring concrete structures and ... More Information

Europe's $45BN Mega Tunnels through the Alps

Discover the record-breaking network of tunnels being constructed beneath the Alps. This video explores the top 6 longest tunnels in the region, .. More Information

AFRY secures contract for Switzerland's Twann Tunnel project

Construction oversight of the Twann Tunnel in the country. The tunnel on the Lake of Bienne is intended to ease traffic congestion in Twann by ... More Information

Line 5 Tunnel Project: Public comments now open for proposal to build under Straits of Mackinac

"The purpose of the project is to facilitate the construction of a tunnel beneath Lake Michigan bottomlands to replace the Line 5 dual pipelines ... More Information

ECRL Breakthrough: Genting Tunnel Becomes SEA's Longest Rail Tunnel

Genting Tunnel's construction used both Tunnel Boring Machines (TBM) and traditional drill-and-blast methods. The TBMs, built in China and ... More Information

Sydney tunnel factory creates 700 manufacturing jobs

The factory will support two of the largest tunnel boring machines (TBMs) in the Southern Hemisphere, set to arrive later this year. Once ... More Information