On 19/04/2021 - about one month after construction works started, they broke through. The works were below the riverbed of the Isarco river for the future Brenner Base Tunnel railway. Excavation below the river was only possible after freezing the soil with liquid nitrogen and then maintaining low temperatures by circulating brine.
Works were carried out with a percussion hammer, which breaks up the soil reaching a 1.5 m/day average daily advancement. After the excavation works have been completed, the next step will be the final concrete lining of the tunnel. During 2020 one of the other tunnels was excavated using soil consolidation and two other tunnels are yet to be dug using the same method. For further information please click here, at/16 and it/103 for the tunnelbuilder archive and also visit https://www.bbt-se.com/en. 16/21.
13.03.2025 Switzerland
14.03.2025 Slovakia
17.03.2025 Norway
17.03.2025 France
19.03.2025 Germany
19.03.2025 Norway
21.03.2025 Spain
24.03.2025 Romania
24.03.2025 Greece
24.03.2025 Austria
24.03.2025 Croatia
26.03.2025 Finland
27.03.2025 Spain
28.03.2025 France
31.03.2025 Sweden
01.04.2025 Germany
01.04.2025 Poland
04.04.2025 Austria
07.04.2025 France
07.04.2025 Spain
08.04.2025 Netherlands
14.04.2025 Switzerland
25.04.2025 Norway
16.05.2025 Switzerland