While Flavia is only 300 m from its final destination and Ida has already passed the Werner fault zone, the TBM Wilma reached its first kilometre of excavation at 10:40 on Sunday 2 March after having passed the Schmirntal fault zone. Wilma is the feminine form of Wilhelm, which derives from “willio” (will) and “helm” (protective helmet).
On 18 September 2024, the TBM Wilma and its twin Olga had respectively begun excavating the west and east line tunnels (7.5 km) in the northerly direction towards Innsbruck. The segments, installed by the two TBMs for the final lining of the tunnels, reach the H53 Pfons-Brennero construction site by rail, thus avoiding the transit of trucks in the Wipptal valley.
For further information on the project click here, at/16 and it/103 for the tunnelbuilder archive and also visit https://www.bbt-se.com/. 10/25.
02.01.2026 Germany
06.01.2026 France
12.01.2026 Austria
14.01.2026 Netherlands
15.01.2026 Spain
20.01.2026 Romania
23.01.2026 Switzerland
23.01.2026 Ireland
26.01.2026 Italy
26.01.2026 Germany
29.01.2026 Bosnia and Herzegovina
04.02.2026 Germany
06.02.2026 Spain
09.02.2026 Norway