On 14 May 2024 the TBM Ida, launched back in June 2023, reached its first 3 km of excavation towards the south, in the West line tunnel, advancing an average of 13 m/day and extracting 342,060 m³ of rock. The TBM has a further 5.4 km to drive.
TBM Ida, has already passed the critical fault zones called Viggartal and Walzn without any problems. The other TBM Lilia - has now excavated 2735 m and is also preparing to reach the 3 km milestone.
The TBMs have so far installed lining rings consisting of six precast concrete segments weighing 60 t each: to date, some 17,300 segments have been laid in the two tunnels, produced by the in-house factory and thus avoiding around 27,000 road trips by trucks.
For further information on the project click here, at/16 and it/103 for the tunnelbuilder archive. Visit https://www.bbt-se.com/. 21/24.
20.10.2025 Romania
21.10.2025 Slovakia
27.10.2025 Italy
27.10.2025 Romania
30.10.2025 France
30.10.2025 Romania
03.11.2025 Romania
04.11.2025 Germany
04.11.2025 Slovakia
05.11.2025 Germany
06.11.2025 Romania
10.11.2025 Bosnia and Herzegovina
11.11.2025 Spain
13.11.2025 Switzerland
21.11.2025 Switzerland
27.11.2025 Switzerland
09.12.2025 Switzerland