On 14 May 2024 the TBM Ida, launched back in June 2023, reached its first 3 km of excavation towards the south, in the West line tunnel, advancing an average of 13 m/day and extracting 342,060 m³ of rock. The TBM has a further 5.4 km to drive.
TBM Ida, has already passed the critical fault zones called Viggartal and Walzn without any problems. The other TBM Lilia - has now excavated 2735 m and is also preparing to reach the 3 km milestone.
The TBMs have so far installed lining rings consisting of six precast concrete segments weighing 60 t each: to date, some 17,300 segments have been laid in the two tunnels, produced by the in-house factory and thus avoiding around 27,000 road trips by trucks.
For further information on the project click here, at/16 and it/103 for the tunnelbuilder archive. Visit https://www.bbt-se.com/. 21/24.
30.03.2026 Italy
31.03.2026 Ireland
07.04.2026 Austria
08.04.2026 Norway
09.04.2026 France
09.04.2026 Germany
14.04.2026 United States
23.04.2026 Sweden
24.04.2026 United Kingdom
24.04.2026 Switzerland
27.04.2026 Italy
27.04.2026 Switzerland
30.04.2026 Sweden
30.04.2026 Switzerland
04.05.2026 Switzerland
04.05.2026 Slovakia
04.06.2026 Switzerland
07.07.2026 Germany
31.12.2031 Germany