Norway

Norway, Akershus - no/43

Railway

  Three tenders invited for the doubling of the Sandvika-Asker railway, deadline 31st October. Contract JA1 is to build 3,225 m of double-track tunnels from Solstad to Hí¸nsveien, a 320 m access tunnel and option for a 400 m tunnel from Asker centre. Contract JA2 is for 2,715 m of double-track tunnels from Jong to í…stad, a 120 m access tunnel and option for a 200 m tunnel from Solstad to Asker. Contract JA3 is JA1 + JA2 contracts. Support with rockbolts, shotcrete and steel arches. Visit http://ted.eur-op.int, documents S 197-135100, S 196-134351 and S 196-134352. Contact Jernbaneverket, Oslo, fax +47 22 455860, e-mail utbygging@jbv.no or visit www.jernbaneverket.no 43/01. Cross section of 111 sq m. Hard rock TBM and drill/blast through Silurian sedimentary rock, mainly limestone. Norconsult involved as consulting engineers. JA3 tunnelling to cost US$100 million, of which US$55 million for JA2, to be 100% financed by Norwegian State. Bidders will be known early December, 2001. Contract awards for end-January, 2002. JA1 tunnelling to start in mid-summer, 2002. JA2 tunnelling to start early-February, 2002. Completion scheduled for mid-summer, 2004. Visit www.norconsult.no 44/01. Award to Veidekke of the Sandvika-Asker railway dualling requiring a 490 m 96 sq m double-track tunnel and two 480 m 56 sq m single-track tunnels. All cut-and-cover. Moraine (40%), clay (57.5%) and rock (2.5%). Double-track tunnel to cost €7 million and single-track tubes €3.2 million with time frame May 2002-March 2003 and March 2002-January 2003 respectively. Visit www.veidekke.no 05/02. Sandvik Tamrock has been awarded the contract to supply two computerized full data Axera tunnelling jumbos to be used by contractor Mika AS to excavate the tunnel from Asker to Jong, which is part of a double-track railway between Oslo and Asker. The equipment contract, valued at over NOK20 million, also covers the supply of drill steels as well as service for two years. Delivery will start in March, 2002. Visit www.sandviktamrock.com and www.sandvik.com 07/02.Sandvik Tamrock AS is delivering a third full-data tunnelling jumbo to Mika AS. The Tamrock Axera T11 DATA three-boom fully computerized jumbo with basket boom will start up a third face in May, 2003. Visit www.sandviktamrock.com 05/03.Negotiated procedure, deadline 17th October, 2003 for design and installation of contact lines, low voltage and remote control equipment on the new Sandvika-Asker double-track line, section Sandvika-Jong-Asker. Work to be done in the Jong-Solstad tunnel (3,485 m) and in the Solstad-Asker tunnel (3,790 m) and at grade between the tunnels (540 m). Contact line installations, ventilation fans (smoke and frost), emergency lighting installations, and high voltage and low voltage installations must be installed in the tunnels. Includes also works at Sandvika and Asker stations. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=172405-2003, OJ S 191, or contact Jernbaneverket, Sandvika, fax +47 22455860. E-mail hsg@jbv.no 42/03.Negotiated procedure, deadline 1st June, 2004 for detailed plans for a 5.5 km double-track rock tunnel between Lysaker and Sandvika on the Skoyen-Asker section. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=071793-2004, OJ S 84, or contact Jernbaneverket, Oslo, fax +4722455800. E-mail anne.kathrine.kalager@jbv.no 19/04.Multiconsult won a contract for the detailed and construction plans for a 5.5 km double-track rock tunnel between Lysaker and Sandvika on the Skoyen-Asker section. Asplan Viak won another contract for development plans. Visit www.multiconsult.no and www.asplanviak.no 46/04.Open call for tenders, deadline 8th January, 2007 for construction of a 1.2 km railway tunnel, including securing, pre-injection, waterproofing and frost protection, etc. and approx. 800 metres of railway at ground level. Read E-News Weekly 19/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=205551-2006, OJ S 193, or contact Jernbaneverket, Oslo, fax +47 22455800. E-mail kkn@jbv.no 42/06.Open call for tenders, deadline 29th January, 2007 for contracts LS-02 and LS-03 of the Lysaker-Sandvika double-track railway tunnel. Contract LS-02 Skallum comprises the tunnel works between Lysaker west and Fossveien. Contract LS-03 Fossveien comprises the tunnel works between Skallum and Sandvika east. Both railway tunnels are approx. 1,800 m long with a cross section of approx. 110 sq m. The construction of the tunnel has been divided into four contracts, one of which has been previously tendered. The final contract will be announced in the near future. Read E-News Weekly 19/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=223334-2006, OJ S 209, or contact Jernbaneverket Infrastruktur Utbygging, Oslo, fax +47 22455800. 46/06.Negotiated procedure, deadline 3rd January, 2007 for hire of an engineering design manager for the tunnel and open air zone for the Lysaker-Sandvika railway dualling. The project is divided up into four main contracts. The primary assignments for the engineering design manager are to assist the project manager/construction managers in following up the consultants for the tunnel and open air zone works as well as following up the development of work drawings and management, operations and maintenance documentation. Also included is coordination of the engineering design works for all trades in the project. Read E-News Weekly 19/2006. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=238703-2006, OJ S 222, or contact Jernbaneverket Infrastruktur Utbygging, Oslo, fax +47 22455800. E-mail aie@jbv.no 48/06.Negotiated procedure, deadline 15th January, 2007 for construction management for the Lysaker-Sandvika railway dualling. Read E-News Weekly 46/2006 & 19/2006. Click no/43. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=249745-2006, OJ S 233, or contact Jernbaneverket Infrastruktur Utbygging, Oslo, fax +47 22455800. E-mail aie@jbv.no 51-52/06.Accelerated negotiated procedure, deadline 5th January, 2007 for vibration measurements as part of the construction of the new double track railway between Sandvika and Lysaker, including approx. 5.5 km of tunnel. Read E-News Weekly 46/2006 & 19/2006. Click no/43. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=255921-2006, OJ S 239, or contact Jernbaneverket Infrastruktur Utbygging, Oslo, fax +47 22455800. E-mail tvevid@jbv.no 51-52/06.Jernbaneverket, the Norwegian National Rail Administration, contracted Skanska to build a new railway section. The contract amount is NOK498.4 million. The contract involves the new construction of a 2.8 km section of double track between Skí¸yen and Asker, west of Oslo. The project is one of four sections of the new railway line between Lysaker and Sandvika. Skanska’s assignment includes all work except track laying. The section includes a 1.2 km railway tunnel, including securing, pre-injection, waterproofing and frost protection, etc. and approx. 800 metres of railway at ground level. Construction begins in March and is scheduled for completion in July 2011. Visit www.skanska.no 10/07.Veidekke has signed a contract with Jernbaneverket, the national rail administration, for the Skallum substructure (contract LS-02), which is part of the new double-track railway line between Skí¸yen and Asker. The contract price is NOK365 million. The contract involves tunnelling from an access tunnel at Skallum in Bí¦rum. Veidekke will establish the approximately 420 m-long access tunnel down to the main tunnel for the double-track line. It will drive approximately 800 metres of tunnel in the direction of Lysaker and 800 metres in the direction of Sandvika. Both tunnels will be driven to connect up with neighbouring contracts. The work includes rock blasting, securing and other structural work inside the tunnel. The work will commence on 11th April and be completed by 1st August, 2010. Visit www.veidekke.no 12/07.Negotiated procedure, deadline 16th April, 2007 for contracting of five control engineers for the Lysaker-Sandvika line, for assistance to the construction manager with quality control. Click no/43. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=69506-2007, OJ S 56, or contact Jernbaneverket, Oslo, fax +47 22455800. E-mail aie@jbv.no 14/07.NCC Construction signed on 10th April an agreement worth approximately NOK372.7 million with Jernbaneverket, the railway infrastructure developer, for contract LS-03 Fossveien, which is part of the new double-track railway on the route between Skí¸yen and Asker on the Lysaker to Sandvika line, west of Oslo. A 240 m-long tunnel is to be constructed down by the main line for double-track railway services at Fossveien in Bí¦rum. Subsequently, a 1,050 m-long tunnel will be constructed towards Lysaker and a 750 m-long tunnel towards Sandvika. These two tunnels will connect with other tunnel contracts. Work will commence on 2nd May and is scheduled for completion on 1st August, 2010. The works include blasting, securing and other interior construction work in the tunnel. Visit www.ncc.info 16/07.SBV Consult pocketed a NOK6.3 million contract to undertake vibration measurements as part of the construction of the new double track railway between Sandvika and Lysaker, including approx. 5.5 km of tunnel. Read E-News Weekly 16/2007, 46/2006 & 19/2006. Click no/43. Visit www.sbv-consult.no 27-28/07.Negotiated procedure, deadline 13th December, 2007 for quality control and follow-up of works on the Lysaker-Sandvika railway dualling. Click no/43 to know details about the tunnels involved. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=268468-2007, OJ S 220, or contact Jernbaneverket, Oslo, tel. +47 22455992. E-mail aie@jbv.no 47/07.Tunnel and GeoConsult, and independent consulting engineers Sigmund Bakk and Lise Backer have been contracted by the Norwegian National Rail Administration for quality control assistance to the construction manager for the Lysaker-Sandvika line. Read E-News Weekly 16/2007, 46/2006 & 19/2006. Visit www.tunnelandgeoconsult.com 48/07.Negotiated procedure, deadline 8th May, 2008 for electrical installations (high and low voltage systems) for the new 6.5 km double track railway between Lysaker and Sandvika, 5.5 km of which is in tunnel. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=71126-2008, OJ S 52, or contact Jernbaneverket, Oslo, tel. +47 91656257. Visit solgei@jbv.no 13/08.Negotiated procedure, deadline 8th May, 2008 for telecom installations for the new 6.5 km double track railway between Lysaker and Sandvika, with approximately 5.5 km of tunnel. The installations include tunnel radio, emergency telephones and fibre installations. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=71125-2008, OJ S 52, or contact Jernbaneverket, Oslo, tel. +47 91656318. Visit jto@jbv.no 13/08.Contract for telecommunications installations for 6.5 km section of new double railway track in Baerum municipality for Lysaker-Sandvika, of which 5.5 km in tunnel, awarded by Jernbaneverket to T Connect AS of Manglerud, Oslo. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=292852-2008 More from Olaf Bjerknes, tel +47 9943 4144, e-mail olbj@jbv.no 46/08.Contract for high and low voltage electrical installations on 6.5 km section of Lysaker-Sandvika line through Baerum municipality, of which 5.5 km is in tunnel, awarded to YIT Building Systems of Etterstad, Oslo, value EUR12 million. Jernbaneverket contact is Jarle Tommervik, tel +47 9165 6318, e-mail jto@jbv.no. Visit archive file no/43 for a full history of the contracts for dualling of the Sandvika-Asker line. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=4562-2009 02/09



Permalink

Invitation to tender using negotiated procedure, deadline 18.03.2011, to qualify as consultant for preparation of construction plan for fire protection measures in Oslo tunnel on Etterstad-Lysaker line. Further information, specs and docs from Bard Hjelman at Jernbaneverket in Oslo, tel +47 05280, fax +47 22455499, website www.jernbaneverket.no to where tenders or requests to participate must be sent. Contract details at www.doffin.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=056673-2011. 08/11.



Permalink

Invitation to tender using negotiated procedure, deadline 20.02.2012, for installation of fire water and smoke ventilation measures in Oslo tunnel on Etterstad-Lysaker line. Contract duration 12.04.2012 to 23.12.2013. 4 km of fire water lines required with outlets at 100 m intervals. 2.1 MW installed power required, with 49 smoke ventilation fans. Register interest and obtain additional information at www.doffin.no/Search/Search_Switch.aspx?ID=247975. Further information, specs and docs from Utbyggingsdivisjonen at Jernbaneverket in Oslo, tel +47 05280, fax +47 22455499, website www.jernbaneverket.no to where tenders or requests to participate must be sent. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=024200-2012. 04/12.



Permalink

Norway, Sogn og Fjordane - no/42

Tyin Hydropower

      Selmer Skanska to build Tyin hydro plant on í˜vre í…rdal river for Norsk Hydro. Contract value NOK512 million (SEK628 million) includes a subterranean power station, pumping facilities, shafts and 19 km of tunnels. Preparatory work has commenced. Completion October, 2004. Visit www.selmer.skanska.no 41/01.  1.54 km-long access tunnel completed June, 2002 and powerhouse excavation underway in granite. 2.7 km-long x 46 sq m tailrace under development for breakthrough June, 2003 using Atlas Copco Rocket Boomer WL3 C to drill 90 holes/round at 5.2 m-long x 48 mm-diameter under 1.5 km rock cover. 12-15 resin anchored bolts/round, 2.4 or 4.0 m-long, with shotcrete. Bi-directional drives underway from 350 m-long access tunnel at mid-point of headrace, using Atlas Copco 353 S drillrigs and Cat 963B loaders with Gjerstad side tipping buckets stationed at each face, with single crew alternating. Granite towards powerstation, phyllite towards lake. Surge shaft chamber complete, and Skanska Raise Boring mobilizing refurbished Robbins 97 RLC to bore 463 m-deep x 4.04 m-diameter shaft. 2.4 km-long draw off tunnel between Lakes Tyin and Toroholmen underway using Schaeff ITC 312 loader and Moxy MT25 trucks. Project on schedule. Visit www.selmer-skanska.no and www.skanskaraiseboring.com. Read E-News Weekly # 20. 46/02.Total of 4,500 rounds blasted to remove 680,000 cu m of rock, with some 27,086 rockbolts and 15,100 cu m shotcrete installed by 160 workers. Excavation completed during 2003, with the final blast in the tailrace end-May, and the headrace from Biskopsvatn to the power station breaking through on 10th July. The draw-off tunnel at Torolmen was finished at the end of July, with the lake tap left ready drilled for blasting, scheduled to take place in mid-2004. The piercing of Ardalsvatn from the tailrace will be carried out in Spring, 2004. Nearly 21 km of tunnel and 45,000 cu m of powerstation were excavated in just 19 months, involving 600,000 manhours, without a single serious accident. More from magnar.myklatun@skanska.no or visit www.boomer-rig.com 09/04.



Permalink

Norway, Sí¸r-Trí¸ndelag - no/41

Highway

Prequalification, deadline 15th October, 2001, for construction under DBFO contract of the Oysand-Thamshamn section of the E39 highway between Klett and Baardshaug, including 10 km of tunnels. Visit http://ted.eur-op.int, document S 186-127933, or contact Norwegian Public Roads Administration, Oslo, fax +47 22073673. Visit www.vegvesen.no/sortrondelag 41/01. Tenders invited, deadline 10th December, 2001, for design and construction. Visit http://ted.eur-op.int, document S 194-133062, or contact Norwegian Public Roads Administration, Oslo, fax +47 22073673. Visit www.vegvesen.no/sortrondelag 42/01. Shortlisted candidates for the DBFO contract for the Oysand-Thamshamn section between Klett and Baardshaug on E39 are Skanska and Laing Investment; Veidekke and Hochtief; and Bouygues and AS Anlegg. Ten kilometres of tunnels will be necessary. An award is planned for March 2003. Visit www.vegvesen.no/sortrondelag 37/02.Orkdalsleden, a consortium formed by Laing Investments and Skanska BOT, has been chosen by the state roads agency as preferred bidder for a £140 million contract, the first PPP programme in Norway. The project involves a new 27 km-long route on E39 including 10 km of tunnels. Selmer Skanska is the construction and operations partner in the consortium. Concession for a period of 25 years. Visit www.vegvesen.no 05/03.To excavate six tunnels totalling 10.5 km on subsection Oysand-Thamshamn (22 km) of E39 motorway section from Klett to Bí¥rdshaug on the Norwegian coast, Selmer Skanska will use the drill/blast method. The tunnels are Brekk (1,260 m), Mannsfjell (1,740 m), Svalnes (770 m), Naust (275 m), Viggja (2,700 m) and Storsand (3,750 m). All single tubes with two lanes, profile T9.5 m, blasting cross section approximately 70 sq m. Geology for Storsand consists of gneiss. Support with rockbolts and shotcrete. Steel fibre-reinforced shotcrete when necessary. Muck removal with dumper trucks. Main engineering firm is Aas-Jacobsen. Tunnel cost: NOK50,000 per metre approximately. Construction period from April 2003 to September 2005. The Storsand tunnel will be blasted from December 2003 to October 2004. To date, one kilometre has been excavated at different work sites, out of the total tunnel length. This is the first ever motorway concession in Norway, to last 25 years from 1st September, 2005. Visit www.skanska.no 40/03.



Permalink


Orkdalvegen AS from Oslo secured the EUR 23.97 million (NOK240 million) contract, excluding VAT, for tunnel upgrading on the E39 Klett - Bardshaug. Contact Norwegian Public Roads Administration, attn Arild Gjerde, Moss, email arild.gjerde@vegvesen.no. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=665318-2021. Ref.n. 20/271. 52/21. 



Permalink

Norway, Oslo - no/40

Highway

Award to AAS Jakobsen of engineering design contract for 1.3 km-long road tunnel between Storo and Carl Berners Square. Construction tender scheduled for late-2002. Visit www.vegvesen.no 38/01. Open tendering, deadline 18th December, 2001, for cleaning the ceiling, walls, floor, and technical equipment (traffic signs, lighting, ventilation fans, anti-fire devices, cameras, crossing gates) in the following tunnels: Bjí¸rvika (150 m), Bryn (2 x 240), Festning (2 x 1,800), Framnes (2 x 123), Hammersborg (2 x 225), Smestad (2 x 500), Storo (136), Tí¥sen (2 x 1,284), and Vaterland (337). Everything except cameras to be cleaned with pressure water and brushes. Cameras to be hand cleaned with low pressure water. Visit http://ted.eur-op.eu.int, document S 220-151919 or contact Statens Vegvesen, Oslo, fax +47 23210803. 48/01.Open tendering, deadline 2nd January, 2002, for injection works to stop water leaks in the Bryn tunnel (2 x 240 m) and Festning (2 x 1,800). Visit http://ted.eur-op.eu.int, document S 228-157253 or contact Statens Vegvesen, Oslo, fax +47 23210803, valmol@vegvesen.no 50/01.



Permalink

Open invitation to tender, deadline 27.03.2015, for purchase of traffic systems in the Opera and Valerenga tunnels on E6/E18 at Oslo. Contract value EUR232,024-348,047, excluding VAT. For electronic access to information https://kgv.doffin.no/ctm/Supplier/Documents/Folder/126484. Contact Statens vegvesen Region East, attn Bjorn Moholt, Lillehammer, tel +47 91361164, e-mail bjorn.moholt@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=49751-2015. Ref.n. 2014155636. 07/15.



Permalink

Norway, Slottspark - no/39

Highway

Open invitation to tender, deadline 29th August, 2001, for environmental impact study of three alternative routes for $50 million, 1.3 km-long tunnel beneath Royal Palace park. Visit www.vegvesen.no and www.norconsult.no 32/01.Contract award worth NOK2.7 million to Asplan Viak for the environmental impact assessment studies of new routes for the Slottspark tunnel. Visit www.asplanviak.no or www.vegvesen.no 01/02.



Permalink

Norway, Oslo-Drammen - no/38

Railway

Three twin-track, single 115 sq m drill/blast tunnels, 3.8 km-long, 4 km-long and 5.5 km-long in design for new $700 million, 19 km section of line for construction start late-2001. Tender for first tunnel, deadline mid-September, available shortly from www.jerbaneverket.no Visit www.norconsult.no 29/01.



Permalink

Norway, Nittedal - no/37

Highway

Open invitation to tender, deadline 30th March, 2001, for construction of 2.6 km-long road tunnel for Statens Vegvesen Akerhus, fax +47 670 59950. Visit www.vegvesen.no 11/01. Open invitation to tender, deadline 26th April, 2001, for road construction with 2.65 km-long tunnel. Contact Statens Vegvesen Akershus, fax +47 639 74253 or visit www.vegvesen.no 13/01.Award of construction contract for 2.6 km-long tunnel with 2.1 km-long approach road to AF Spesialprosjekt. Visit www.vegvesen.no/akershus 44/01.



Permalink

Norway, Ringeriks - no/36

Railway

Line will link Sandvika and Honefoss and will be built with either 28.9 route km of tunnels if route via Kroksund and Busund is chosen, or 37.6 km if via Sundvollen and Asa. Rock is volcanic with sandstone. Choice of TBM or drill/blast, and single or twin tubes. Cost range $375 million to $450 million for construction 2006-2009. Tenders for design expected early 2002. Visit www.jernbaneverket.no 12/01.



Permalink


Norconsult/Aas-Jakobsen/Asplan Viak from Sandvika secured the EUR5.36 million contract, excluding VAT, for  a consultancy assignment for the Ringerike Line/E16 Hogkastet-Honefoss. For electronic access to information: http://eu.eu-supply.com/app/rfq/rwlentrance_s.asp?PID=158164&B=JERNBANEVERKET. Contact Jernbaneverket, the Norwegian National Rail Administration, attn Lisbeth Smedbraten, Oslo, e-mail marianne.naro@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=240887-2016. Ref. 201600518. 28/16.




Permalink

Norway, Tonsberg - no/35

Highway

Tenders expected January, 2001 for design of single-tube, 1.7 km-long ring road tunnel to be constructed in 2003 by drill/blast with rockbolts and shotcrete support for opening 2006. Contact www.vegvesen.no/vestfold for further details. 02/01.



Permalink

Norway, Ski - no/34

Railway

Proposed 13 km-long railway between Rosenholm and Ski will require 6+ km of tunnels, longest of which will be 4 km and 1.5 km. Tenders for engineering design expected mid-2001 for construction start in 2005. Visit www.jernbaneverket.no/prosjekter 03/01.



Permalink