Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Archive Search

India

India, Sikkim - in/24

Hydro

Teesta V will have an underground powerhouse 99.5 m x 50.5 m x 23 m-high to house 3 units of 170 MW and transformer cavern will be 85 m x 15 m x 25 m-high with an 8 m x 8 m access tunnel. Three 176 m x 4.7 m-diameter steel-lined vertical pressure shafts and a 92 m-high x 25 m-diameter surge shaft. The headrace will be 17.78 km-long x 9.5 m-diameter circular section with three 132 m-long x 6 m-wide D-shaped tailrace tunnels. Two 12.5 m-diameter diversion tunnels 550 m and 600 m in length will be required on the right bank of the Teesta river. Three desilting chambers 315 m-long x 20 m-wide x 22.5 m-high downstream of intake with 4.5 m-diameter circular section silt flushing tunnels. Five sites have been identified for 7 m x 7 m access adits for construction. Pre-construction work underway on 7-year programme. Visit www.nhpcindia.com October 2000.



Permalink

India, Uttar Pradesh - in/23

Dhauliganga Hydro

280 MW project financed by JBIC underway with start of construction work on main underground components by National Hydroelectric Power Corporation Ltd. Visit www.nhpcindia.com August 2000.



Permalink

India, Maharashtra - in/22

Arphal Water Transfer

  Kvaerner Cementation India underway on 16.6 km, 30 sq m cross section arched, unsupported tunnel in basalt using two Atlas Copco Boomer 281 drillrigs on four faces accessed from two adits. Both portals sub-contracted. More from info@kvaerner.com . October 1999.



Permalink

India, Kashmir - in/21

Dul Hasti Hydro

  Jaiprakash getting underway at Jammu using nine Atlas Copco L2D Boomers equipped with 1838 Rocket drifters. October 1999.



Permalink

India, Baspa - in/20

Hydro

  Private power project being developed by Jaiprakash Industries for commissioning 2002. Powerhouse excavation complete and headrace tunnel well underway using Atlas Copco Boomer 352s. October 1999.



Permalink

India, Himachal Pradesh - in/19

Hydropower

  Jaiprakash underway using Robbins 8.3 m hardrock TBM to bore headrace in quartzite and six Atlas Copco 352 and 353 drillrigs mining the chambers. Norconsult is involved as designer. October 1999.Hindustan Construction Company has been awarded Stage III of the Chamera hydroelectric project by the National Hydroelectric Power Corporation (NHPC). Stage III of the scheme is located in the Chamba district of Himachal Pradesh on the banks of the river Ravi. The project comprises of a 68 m-high dam, an underground power house (3 units of 77 MW each), a 340 m-long 8.2 m-diameter horseshoe-shaped diversion tunnel, a 15.93 km-long 6.5 m-diameter concrete-lined headrace tunnel, a 18 m-diameter 110 m-high surge shaft, and two underground parallel desilting chambers (each 300 m x 13 m x 22 m in size). The project is valued at Rs5.05 billion and has a completion period of 60 months. Visit www.nhpcindia.com/english/press/uri2chamera3.htm and www.hccindia.com 46/05.



Permalink

India, Himachal Pradesh - in/18

Nathpa Jakri Hydro

  Run of river 1,500 MW project with 27 km x 11 m-diameter circular headrace tunnel developed by jv of Impregilo and Hindustan Construction Company using nine Atlas Copco 352 and three 353E equipped with 1440 Rocket drifters. Work continuing on barrage and desilting chambers by jv of Continental and Foundation Corporation of Canada. Powerhouse excavation completed by Jaiprakash Industries together with 700 m tailrace. Alimak raise climbers in use in penstock development. On target for commissioning 2001. October 1999.



Permalink

India, Bombay - in/17

Water Supply

  Bidding for final lot of four contracts that have been undertaken since mid-80s to provide fresh water to Bombay treatment plants. This package is for 12 km of 3.5 m-diameter tunnel in basalt. First lot completed by Gammon using a Demag TBM; second and third packages completed by Hindustan Construction Company using a Wirth TBM. October 1999.$35 million contract awarded to Hindustan Construction Company for 12 km-long tunnel to be constructed at 60 m depth to supply 355 million litre/day of water to Mumbai and district. Tata Consulting Engineers evaluated bids for Brihanmumbai Municipal Corporation. Sept 2000.



Permalink

India, Bombay - in/16

Sewage Outfall

  Dyckerhoff & Widmann halfway through contract to provide two 3 km-long, 3 m-diameter sewer outfalls using single Wirth TBM in basalt. October 1999.



Permalink

India, Hindustan - in/15

LPG Storage

  Underground facility to be constructed on east coast by South Asia LPG Co Pvt Ltd, a jv of Hindustan Petroleum Corporation and TotalFina of France. Sept 1999. Project design comprises three caverns in rock 145 m below sea level to provide 60,000 t storage capacity. Location underground will eliminate damage by cyclones and reduce potential for sabotage. Completion in early-2003 at estimated cost of Rs2 billion. January 2000.  Four companies have been shortlisted for the country's first underground Liquefied Petroleum Gas (LPG) storage facility at Visakhapatnam. South Asia LPG Company Ltd (SALPG), a joint venture between Hindustan Petroleum Corporation Ltd (HPCL) and the French oil major TotalFinaElf, which is implementing the project, has shortlisted four international companies for executing the project on a turnkey basis. The four companies are S.K. Engineering Co of Korea, LG Engineering and Construction Co.; Sweden's NCC International AB-France's Sofragaz jv, and JGC Corporation of Japan. The four have been asked to submit their detailed financial and technical bids by next month. The project requires a U-shaped cavern at a depth of 162 metres below ground, . The cavern itself will 24 m-high and 317 m-long for a the total storage capacity of 60,000 tons. Construction to start in May or June this year. 05/02.The commissioning of the country's first underground LPG storage facility by SALPG at Visakhapatnam, one of the deepest mined caverns in the world, is scheduled for June 2007. SALPG, a joint venture between Hindustan Petroleum Corporation Ltd (HPCL) and Total Gas & Power India, a wholly owned subsidiary of French company Total, is setting up the mined cavern for LPG storage at a cost of Rs3.3 billion, with a capacity to store 60,000 tonnes of LPG.The internal walls of the storage facility are not subjected to concreting and the natural surface of the rocks deep within the earth would store the LPG. The stored product is prevented from escaping on the principle of hydraulic containment, whereby the cavern is located at such a depth that the water naturally present in the surrounding rock creates a counter pressure higher than the pressure of the stored product, preventing it from migrating. The water pressure in the rock can be enhanced artificially by special water supply systems (water curtains). In this case, the main storage is located 162 metres below Mean Sea Level (MSL), with the deepest portion being 196 metres below MSL. The underground construction involved excavation of a 4-m diameter vertical shaft that extends up to a depth of 196 m below MSL. At 144 m below MSL, the operation shaft is connected to the water curtain gallery on the basis of the containment principle. Further down, at 178 m below MSL, the operation shaft is connected to the main storage zone by a 4.5 m-high tunnel, called the cavern operation shaft lower connection. The main storage cavern comprises components such as upper shaft connection, east and west cavern main galleries and intermediate connection, which together give a volume of 123,000 cubic metres. The work involved continuous underground blasting of rock, which was powdered and lifted up the shaft for disposal outside. Larsen & Toubro is undertaking the cavern construction work. Visit www.lntecc.com 50/06.



Permalink