Open invitation to tender, deadline 18/06/2021, for construction of 5 underground stations at Boat Club, Nandanam, Panagal Park, Kodambakkam, Kodambakkam flyover including underground cross over at Panagal Park Station and associated 4.8km twin tunnel, cut&cover, U section and ramp project start from km 5+150 to end km 10+027 for the Chennai metro (Down line). For tender documents click here. Duration of the contract is 48 months. The pre-bid both online and offline meeting shall be conducted at the CMRL admin building on 06/04/2021 at 15:00 Hrs.
Contact Chennai Metro Rail Ltd, Chennai , tel 044-2379 2000, Extn: 22347, fax044-2379 2200,
email gurunath.reddy@cmrl.in. For further on the tender, please click here. Ref.n. CMRL/CON/PHASE-II/C4-UG-02/2021. 08/21.