The joint venture between Traylor Infrastructure Canada
(60%) and Aecon Infrastructure Inc (40%) has been awarded a $267 million
contract by Metro Vancouver (Greater Vancouver Water District) for the Second
Narrows Water Supply Tunnel project in British Columbia. The scope of work
includes construction of two shafts, one on each side of Burrard Inlet,
connected by a 5 m in diameter and 1,100-m tunnel. The north entry shaft will
be in North Vancouver and approximately 60 metres deep, while the south exit
shaft will be in Burnaby and approximately 110 m deep. The project is scheduled
to begin in late 2018, with completion in 2022. Visit http://www.metrovancouver.org, http://www.traylor.com/ and http://www.aecon.com. 44/18.