Open call for bids, deadline 21st August, 2003 for project engineering for the Skantull-Solberga power tunnel. The complete tunnel between Skantull and Solberga via Örby will be approximately 6.4 km in length, of which 5.1 km will be a new tunnel which will generate 90,600 cubic metres. The purpose is to move an existing aboveground power line into the tunnel. Cross sections: 17.7 sq m (new tunnel) and 12.5 sq m (existing tunnel). Geology is mostly granite. Drill/blast method from five drives. Support technique and mucking-out equipment not yet decided. Feasibility study by Scandiaconsult (SCC), WSP and Bergab. Tenders for tunnelling in April 2004. Estimated cost: SEK400 million financed by Stockholms Gatu- och fastigehetskontor. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=105172-2003, OJ S 117, or contact Stockholms Gatu- och fastigehetskontor, Stockholm, fax +46 850826301. E-mail kjell.engvall@gfk.stockholm.se and johan.arvidsson@carlbro.se 27/03.Open call for tenders, deadline 16th October, 2006 for construction of a 7 km cable tunnel from Skanstull to Solberga in south Stockholm, a work tunnel and terminal facility. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=133115-2006, OJ S 125, or contact Stockholms Stads Markkontor, Stockholm, tel. +46 84800000. E-mail tobias.kednert@mk.stockholm.se or ake.stiberg@carlbro.se 28/06.Details are available about the construction of the Skanstull-Solberga cable tunnel in Stockholm. The main tunnel includes sections of 18.3 sq m for a 5,560 m distance (height 5 m) and 20.3 sq m for a 780 m distance (height 5.5 m). For both tunnels the width is 4 m. There are also three work tunnels of 27.4 sq m with a total distance of 780 m and five vertical shafts for cables, ventilation and stairs. They are deep tunnels in rock (mainly gneiss) below the groundwater level. The new tunnel is not allowed to cause sinking of the groundwater level due to existing buildings at the surface and crossing tunnels above the new tunnel. The tunnel is planned to be built by conventional driving by jumbo and explosives in full section, but alternative solutions may be accepted. To stop groundwater, mainly drilling and concrete injection is planned. To support the rock, mainly bolts and shotcrete with and without fibres will be used. Concrete formwork at the tunnel ends. Steel construction in the five shafts. Small rooms for technical equipment are required underground. An invitation to tender is under way, for contact award in December 2006. Construction to start immediately after for end on 31st March, 2010. Click se/30. 33-34/06.Open call for tenders, deadline 29th October, 2006 for contract management for construction of the Skanstull-Solberga tunnel for electrical cables. The main responsibility of the assignment is to ensure, on behalf of the customer, that all contractual requirements are fulfilled. The contract management shall include expert advising and administrative work. Click se/30 for details about the tunnel. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=182698-2006, OJ S 171, or contact Stockholm Stad Markkontoret, Stockholm, fax +46 13312490. E-mail toblas.kednert@mk.stockholm.se or request@opic.com 38/06.Open call for tenders, deadline 22nd February, 2007 for construction of the Hjorthagen cable tunnel. This is an approx. 1.1 km tunnel, also including a vertical shaft and a 300 m work tunnel. Read E-News Weekly 41/2006 for more details. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=250227-2006, OJ S 234, or contact Markkontoret, Stockholm, fax +46 13312030. E-mail anna.pramsten@mk.stockholm.se 51-52/06.Oden Anläggningsentreprenad pocketed a SEK335 million contract to build a 7 km cable tunnel from Skanstull to Solberga in south Stockholm, a work tunnel and a terminal facility. Visit www.oden.nu 05/07.
Invitation to tender using negotiated procedure, deadline 10.02.2010, for construction of 900 m-long Moerby rock tunnel between Karlsroveagen and Kevinge golf course with associated accesses and buried cable routes for Swedish Power. Further information, specs and docs from Sofia Hoegfeldt at Svenska Kraftnaet in Sundbyberg, tel +46 87397539, e-mail sofia.hogfeldt@svk.se. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=354834-2009. 53/09.
Invitation to tender using negotiated procedure, deadline 31.10.2011, for marine and land geotechnical and geological surveys along line of proposed TBM-bored City Link transmission tunnel for Stockholm Power division of Swedish Power. Further information, specs and docs from Rolf Axen at Svenska Kraftnaet in Sundbyberg, tel +46 702304426, e-mail rolf.axen@svk.se, to whom tenders or requests to participate must be sent. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=290895-2011. 37/11.
Svenska Kraftnaet the Swedish National Grid a joint venture between Implenia (50%)/Hochtief (50%) (for 4 years) secured the Eur90 million contract to build the Anneberg-Skanstull tunnel in Stockholm.
As the second of four phases in the City Link project, the Anneberg-Skanstull tunnel will help improve electricity supply in the Greater Stockholm region. With a length of around 14 km and a diameter of 5 m, the tunnel is being built around 50 - 100 m below the Swedish capital using a tunnel boring machine. The project also includes six ventilation shafts, elevator systems and the construction of technical buildings for electrical equipment near Anneberg and around the shafts. Completion is scheduled for 2024. The aim of the City Link project is to connect the north (Upplands Väsby) and the south (Huddinge) of Stockholm with a new electricity supply. Visit https://www.implenia.com and https://www.hochtief.com/hochtief_en/201.jhtml?pid=10230. 51/18.
Negotiated invitation to tender, deadline 19/05/2019, for
the monitoring of environmental impact due to drilling, blasting and land works
during the Anneberg-Skanstull cable
tunnel construction in Stockholm. Duration of the contract is from 30/09/2019 to
31/12/2023. For bid documents
https://www.e-avrop.com/svk/e-Upphandling/NoticeLink.aspx?id=44443
where offers must be sent. Contact Svenska
Kraftnat, Sundbyberg, tel +46 708580858, email Carin.Kihlstrom@svk.se. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=190940-2019.
Ref.n. Svk 2018/1225. 17/19.
Negotiated invitation to tender, deadline 19/05/2019, for the monitoring of environmental impact due to drilling, blasting and land works during the Anneberg-Skanstull cable tunnel construction in Stockholm. Duration of the contract is from 30/09/2019 to 31/12/2023. For tender documents
https://www.e-avrop.com/svk/e-Upphandling/NoticeLink.aspx?id=44443 where offers must be sent. Contact Svenska Kraftnat, Sundbyberg, tel +46 708580858, email Carin.Kihlstrom@svk.se. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=190940-2019 http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=190940-2019. Ref.n. Svk 2018/1225. 17/19.