Some 6 km required: 3 km pipejacked at 1.5 m and 1.2 m internal diameter from Lamiako to University awarded to Ferrovial; and 2.3 km at 3.6 m outside diameter to be bored by Robbins TBM through hard rock from 15 m-diameter shaft by jv of ACS, Obras Subterraneas and Sycasa commencing in mid-1999. February 1999.
Open tendering, deadline 6th March, 2002 for the construction of a 3,750 m interceptor sewer in landfill and rock. A 1.2 m-diameter shield boring machine will be used on 50% of the length, traditional means on 10% and open cut on 40 %. Mechanised tunnelling with pipejacking. Tender value of €12.1 million. Commissioning in December, 2004. Engineering consultancy Saitec designed the project. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 14, document 10573-2002 or contact Consorcio de Aguas Bilbao Bizkaia, Bilbao, fax +34 944873110. 08/02.
Open tendering, deadline 6th March, 2002 for the construction of a 2,300 m tunnel to divert the Elguera stream. Outer diameter of 3.60 m and inner diameter of 3 m. A TBM will be used. Shales, marls and limestone. Support with rockbolts, shotcrete, mesh and TH16 steel arches. Tender value of €10 million. Award in June, 2002. Works start in July, 2002 for completion in November, 2004. Engineering consultancy Tecnoconsult designed the project. Visit http://ted.eur-op.eu.int/ojs/en/frame.htm, OJ S 14, document 10574-2002 or contact Consorcio de Aguas Bilbao Bizkaia, Bilbao, fax +34 944873110. 09/02.