March has been a productive month for Tideway with work on the Thames Tideway Tunnel making huge strides ahead of the start of tunnelling later this year.
Tunnel Boring Machines, Millicent and Ursula, are continuing to be assembled on site at Kirtling Street following their arrival last month.
At Chambers Wharf we’ve completed concreting the tunnel shaft wall panels ahead of digging the shaft, a major milestone for the project.
We’ve also got an update on our tree planting programme which will see 400 trees spring up in London. Watch the time lapse video here. 15/18.