Early TBM completion at Lyon metro Line B

07/05/2011
Early TBM completion at Lyon metro Line BOn 23.04.2011 Herrenknecht TBM Agata at Lyon metro Line B reached its exit shaft, some two months ahead of schedule. 300 m of the alignment is beneath the Rhone river. The TBM started the 1.3 km-long drive from Gerland in September, 2010. The final 300 m from Oullins Gare station to the exit shaft took just over a month. Click here and fr/54. Visit www.sytral.fr. 18/11.