Postponed to 27.06.2019 the deadline of the invitation to
tender for the design verification, supply, installation, testing and
commissioning & comprehensive annual maintenance contract (CAMC). The
contract is for 5 years for a tunnel ventilation system (TVS), TVS.Scada,
environmental control system (ECS), ECS and E&M Scada, LV Power System in
ASS. To be implemented on the underground section (Shivaji Nagar, Civil Court, Budhwar Peth, Mandai and
Swargate) of the Pune Metro Rail Project. The duration of the contract is 156
weeks. Contact Pune Metro Rail Project, Pune, tel 020-26051072, email
mahametro.tenders@gmail.com. Visit http://www.punemetrorail.org/download/NIT-UGC03-2019.pdf
and
https://mahametrorail.etenders.in/indexes/tender_details/MTY1.
Bid.n
P1/UGC03/2019. 25/19.