TBM Diggy Scardust has officially started tunnelling for the Scarborough’s 7.8-km subway extension that will bring subway service farther north into Scarborough and accommodate as many as 105,000 daily boardings. Since arriving from Germany late last year, crews at the project’s launch shaft, located at Sheppard Avenue East and McCowan Road, have been busy preparing the excavation required for the TBM launch.
Over the next couple years, the TBM will travel 10 to 15 m/day, making its way south from the launch shaft site towards Eglinton Avenue East and Midland Avenue. It will dig about 6.9 km of the 7.8-km tunnel that will be required to bring seamless subway service farther into Scarborough.
The remaining portion of the tunnel will be built by the contractor for the stations, rail and systems contract. At 10.7 m wide, this will be the first subway tunnel in Toronto to contain two subway tracks operating in both directions.
As tunnelling gets underway, crews have already started work at the project’s extraction shaft site at Midland Avenue and Eglinton Avenue East, where the TBM will be extracted from the ground after completing its tunnelling journey.
For more information click here and ca/36 for the tunnelbuilder archive and also visit https://www.metrolinx.com. 04/23.