Gulermak-TATA Projects JV celebrates the breakthrough of TBM tunnelling on the underground works on Line 1 of the Pune Metro, in India.

In early-November, TERRATEC joined officials from Maharashtra Metro Rail Corporation Limited and workers from Gulermak-TATA Projects Joint Venture to celebrate the breakthrough of a 6.61m diameter TERRATEC Earth Pressure Balance (EPB) Machine, named ‘Mula’, Pune Metro Rail Project, in Maharashtra, India.

The machine holed through the underground Civil Court Station on Pune Metro’s 16.56 km Line-1 (Purple Line). The major milestone saw Gulermak-TATA Projects JV complete twin-tube tunnels between the start of the ramp at chainage 10950 and NATM section at the start of Civil Court Station at chainage 12600, a total of approximately 1650 metres of TBM tunnelling. The TBM’s excavated through Shivaji Nagar Station.

The two 6.61m diameter TERRATEC Earth Pressure Balance (EPB) Machines, the S78 TBM named ‘Mutha’ and the S79 TBM named ‘Mula’, broke through at the end of Sept. and early Nov. at the northern end of a 155-meter scissor crossover, built by the NATM at the start of Civil Court Station launched from near the College of Agriculture at the end of 2019, completing their second drives of the project. It was a good achievement considering the hard rock and being in a densely populated area. Also, during the difficult time of lockdown, Terratec’s field service team was available at the jobsite to support the JV team and the JV team achieved the best monthly progress of 301 metres. In 2019, Maharashtra Metro Rail Corporation Limited (MahaMetro) announced that the joint venture had won both of the twin-tube tunnel packages on the new 16.56km-long north-south metro corridor. The 5km underground section – which runs from the College of Agriculture in Shivajinagar to Swargate and has five stations – is considered the most challenging portion of the line, as it passes under the densely populated areas of Kasba Peth, Budhwar Peth and Mandai market.

The TERRATEC EPBMs feature robust mixed-face dome-style cutterheads designed to work effectively in the compact Basalt that is expected on these contracts at pressures of up to 4 bar. As the TBMs progress, 1,400mm wide by 275mm thick pre-cast concrete lining rings will be installed, which consist of five segments plus a key. Meanwhile, the city’s third TBM (S81) is expected to be launched northwards towards Mandai Station early next year with assembly commencing in December 2020.

Earlier in August, Larsen & Toubro also celebrated the breakthroughs of two 6.57m diameter Earth Pressure Balance machines supplied by TERRATEC for Package 2 (EastWest Corridor) of the 20.7km long Line 1 of the Ahmedabad Metro, in western India. Both machines completed their second drive and the final drive of 1.4km from underground Stations Gheekanta to Shahpur. TERRATEC’s continuing success on projects such as Phase III of the Delhi Metro, Lucknow Metro, Pune Metro, Ahmadabad Metro and Mumbai Metro is a result of tailormade robust TBM design, prompt onsite assistance, readily available stock of TBM spares and highly-skilled specialised TBM support throughout tunnelling operations. ___ For more information visit: www.terratec.co and for Media inquiries info@terratec.co  / pr@terratec.co