On 24.10.2017 the 103 m long TBM named Al Wugeisha Expo 2020
was launched at the Discovery Gardens for tunnel drilling works for the Route 2020
Project. The TBM will cross the underground station near Jumeirah Golf Estates
in January next year. It will drive at a depth ranging from 12.5 to 36 m. The
15 km branch project will start at Nakheel Harbour & Tower on the existing
Red Line at Dubai, then run on 11.8 km of viaduct with stations serving The
Gardens, Discovery Gardens and Al Furjan. The stations at Jumeirah Golf Estates
and Dubai Investment Park would be on a 3.2 km underground section, before the
terminus at Expo 2020 site.
In December 2018, all tunnel drilling works will be
completed. The first of the new Dubai Metro Rolling Stocks will arrive in July 2018,
and construction works for the metro viaducts will be completed in November
next year. All railway works of Route 2020 will be completed in July 2019, and
the trial run of the metro will start in February 2020. The journey time from
the Expo site to Dubai Marina is expected to be 16 min.
Roads & Transport Authority had awarded the contract to
build Route 2020 in June 2016 to the Expolink consortium of Alstom, Acciona and
Gülermak. The EUR2,6 bn (AED10,6 bn) contract includes the supply of 50
trainsets, of which 15 are needed for the new line and 35 to increase capacity
on existing routes. Thales will provide railway systems. Click ae/20 for the tunnelbuilder
archive. Visit http://www.mediaoffice.ae/en/media-center/news/24/10/2017/route-2020-project.aspx
and http://www.dubaimetro.eu/route-2020/.