Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Press Release - Landmark Breakthrough for Robbins TBM ‘Big Tex’

05/08/2022
Press Release - Landmark Breakthrough for Robbins TBM ‘Big Tex’



On 25/07/2022 the large Robbins Main Beam TBM, dubbed ‘Big Tex’, broke through in Dallas, Texas, USA.  

The machine and its continuous conveyor system, for the Mill Creek Drainage Relief Tunnel, successfully bored 8 km (5 mi) in chalk and shale at up to 498 m (1,634 ft) advance in one month.  

Good advance rates were not the only cause for celebration: the unique project required a planned in-tunnel diameter change of the TBM from its original 11.6 m (38 ft) to a more compact 9.9 m (32.5 ft). The first-of-its-kind conversion process was undertaken 2.8 km (1.7 mi) into the bore and was not done inside a shaft or pre-excavated portal. The TBM conversion ultimately provided a more efficient method for the desired product compared to the alternative options. Hopefully the successful conversion proved that this option can be considered for future tunnel projects. 

While there were many detailed steps to the conversion process, precision design of the machine was a key aspect. It has been started with a smaller machine, then a kit or second skin has been made that was slightly larger. And then when the time came, that skin has been taken off. The conversion took about four months and was completed in April 2021. 

The Robbins Main Beam TBM (‘Big Tex’) performed consistently throughout the duration of the tunnel excavation. There were very minor issues and little overall downtime as a result of the TBM itself. Due to the relatively favorable ground conditions in much of the tunnel, including low rock strength and low abrasivity, only eight disc-cutters were changed during the length of tunnel bored at the larger diameter. At the time of diameter change the full dress of cutters was changed, and since that change only 14 cutters have needed replacing. Crews did encounter some fault zones, and installed rock bolts and wire mesh in the tunnel crown as needed.  

With the TBM-driven portion of the tunnel now complete, work can commence to remove the machine from the tunnel and install a final lining. The tunnel is a designated critical infrastructure project for the City of Dallas, providing 100-year flood protection for areas of East Dallas that have experienced severe flooding in the past. Construction work is expected to be complete in late 2024/early 2025. For further information please visit https://www.robbinstbm.com/. 31/22 



NEED QUALIFIED PERSONNEL?