Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Delays in the construction of the Fehmarnbelt tunnel

08/10/2025

The completion of a special vessel designed for immersing tunnel elements has been delayed to such an extent that it will be difficult to meet the target of opening the Fehmarnbelt tunnel in 2029. 

Challenges with the special vessel IVY have significantly delayed the construction of the Fehmarnbelt tunnel between Denmark and Germany. The 18-km-long immersed tunnel is being constructed using concrete elements, each standard element weighing 73,500 t and measuring 217 m in length, which are immersed and assembled on the seabed. 

These elements are substantially heavier and larger than those used in the construction of the Oresund tunnel, which is also an immersed tunnel. The Oresund tunnel, a part of the Oresund link connecting Denmark and Sweden, serves as an important model for the construction of the Fehmarnbelt tunnel. However, the significantly larger scale and increased complexity of the Fehmarnbelt project introduce unique challenges. For example , the work is taking place at an average water depth of 30 m in the Fehmarnbelt, which is twice the depth of the Oresund, necessitating the use of a highly advanced and unique vessel equipped with complex mechanical and electronic systems. 

The specially designed vessel has yet to undergo full testing and receive approval from the relevant authorities, resulting in a delay of 1.5 years in its preparation. Given the current setback with IVY, completing the tunnel within the original timeline is now deemed challenging. 

The Fehmarnbelt tunnel is the world's longest immersed tunnel. IVY is a prototype that has been specially built for the project, and it has taken more time than anticipated.

 

More challenges

It remains uncertain how much of the lost time can be recovered in the coming years. 

When the construction contracts were signed in 2016, the German plan approval for the project had not yet been granted. As a result, specific requirements, such as restrictions on noise emissions from work vessels, could not be incorporated into the contracts. This may make it difficult to accelerate the construction process at a later stage. 

The contracts are nearly 10 years old and were signed before both Covid-19 and the war in Ukraine occurred, and before we knew the scope of the German authorities' conditions. 

Sund & Bælt is in ongoing dialogue with the German authorities to find practical solutions for meeting the requirements related to underwater noise and sediment spill in German waters. In addition, parts of the tunnel trench still need to be levelled with gravel, as supplementary geotechnical surveys have shown that parts of the tunnel trench are around 30 cm deeper than planned. 

The second part of the project, the Danish railway facilities for the Fehmarnbelt tunnel, consisting of around 110 km of new double-track railway from Ringsted to Rødby, is on schedule. 

The overall project will continue to be implemented as a user-paid facility, as stipulated in the Danish Construction Act. 

Click here, dk/14 and de/167 for more detailed information in the tunnelbuilder archive. Visit https://femern.com and https://sundogbaelt.dk.  41/25.



NEED QUALIFIED PERSONNEL?