On the 13th of February 2019 a fifth TBM breakthrough was reached for Mumbai Metro 3 corridor at Chhatrapati Shivaji Maharaj International Airport (CSMIA) - T2 metro station. The TBM Wainganga 3, had started work on the 2nd April 2018 from Pali ground and has now completed its tunnel drive of 1.31 Kms in package 7.
Wainganga 3 made its way through the rocky strata made of Basalt, volcanic Breccia drilling relentlessly for exactly 318 days to attain the breakthrough. It has charted its course from under existing Mumbai Metro Line 1 at Marol Naka and Sahar Elevated Road connecting to CSMIA T-2. The 92-meter long Wainganga-3 bored, on an average, 4.2 meters daily, shaping the tunnel with 937 RCC cement rings.
M/s. Larsen & Toubro and Shanghai Tunnel Engineering Co. Ltd. are consortia partners for the construction of Package-7 which runs from Marol Naka to SEEPZ via MIDC.
The total length of the tunnel is 7.07-km out of which 50% of tunnelling work (i.e. 3.57 km) has been completed to date. For further information please visit https://www.mmrcl.com. 07/19.
Additional links:
https://tunnelbuilder.com/News/Twin-Tunnel-Breakthrough-in-India-.aspx
https://tunnelbuilder.com/Archive/Projects.aspx?&projectcode=in%2f77
https://www.mmrcl.com/sites/default/files/Press%20release_5th%20TBM%20breakthrough%20for%20Mumbai%20Metro%203%20corridor%20at%20Chhatrapati%20Shivaji%20Maharaj%20International%20Airport-%20T2%20metro%20station.pdf
13.03.2025 Switzerland
14.03.2025 Slovakia
17.03.2025 Norway
17.03.2025 France
19.03.2025 Germany
19.03.2025 Norway
21.03.2025 Spain
24.03.2025 Romania
24.03.2025 Greece
24.03.2025 Austria
24.03.2025 Croatia
26.03.2025 Finland
27.03.2025 Spain
28.03.2025 France
31.03.2025 Sweden
01.04.2025 Germany
01.04.2025 Poland
04.04.2025 Austria
07.04.2025 France
07.04.2025 Spain
08.04.2025 Netherlands
14.04.2025 Switzerland
25.04.2025 Norway
16.05.2025 Switzerland