On October 18, 2024, a significant milestone was reached for the Cross River Rail project as a test train entered one of the project’s twin tunnels and arrived at a new underground station ...
More Information
Teams have now completed Woolloongabba - Albert Street and Boggo Road - Woolloongabba sections in both directions, Roma Street to the Northern Portal 1.2 km in the upline and 750 m in the ...
More Information
Teams have now completed Woolloongabba - Albert Street and Boggo Road - Woolloongabba sections in both directions, Roma Street to the Northern Portal 1.2 km in the upline and 750 m in the ...
More Information
Brisbane’s new underground making tracks - Rail tracks installation in the Brisbane's Cross River Rail’s twin tunnels commenced from just south of the future Albert Street station, and ...
More Information
The final delivery of railway tracks arrived at the Northern Tunnel Portal site in May 2022. In total, 9,570 m of railway tracks have been delivered to site and will be installed in the northern ...
More Information
The TBMs - used for excavating the Cross River Rail’s tunnel in Brisbane - have now been taken away from site, allowing the gantry crane to be removed as well: click here for the video. ...
More Information
Excavation, portal structure construction and TBM removal continues in March at the Northern Tunnel Portal site and is on track for completion in mid-2022.
Once the team reaches the required ...
More Information
Today TBM Merle broke through at the Northern Portal site, bringing the Cross River Rail project’s year of tunnelling to an end, click here for the video. The Cross River Rail's twin tunnels ...
More Information
The first of Cross River Rail’s Tunnel Boring Machines has seen the daylight, for the first time in ten months.
The mega project is one of many being delivered by the Palaszczuk ...
More Information
Two 115-tonne roadheaders recently broke through into the cavern of the future Boggo Road station two months ahead of schedule, marking yet another significant milestone for the transformational ...
More Information
Northern Tunnel Portal construction update - Excavation of a TBM extraction box is underway. The extraction box will be used to remove the two TBMs Merle and Else when they arrive in ...
More Information
On 23/08/2021 Merle, the second Cross River Rail’s 1350 t TBM, broke through into the 280-m-long cavern at Roma Street, joining TBM Else, the project’s other machine in the future ...
More Information
On the 06/08/2021 TBM Else (1350 t and 165 m long), the first of Cross River Rail’s two massive TBMs, which had launched from the Woolloongabba site in early 2021 has broken through a ...
More Information
Roma Street station -
The two Cross River Rail TBMs have left Albert Street station in Brisbane’s CBD, where they both arrived between June and July
At the beginning of ...
More Information
Queensland's Coordinator-General seeks your views deadline 04/06/2021, on the eleventh proposed change to the Cross River Rail project, including the effectiveness of the ...
More Information
The 165 m long TBMs Else and Merle, both weighting 1350-t, are excavating the Cross River Rail’s twin tunnels from the launch site at Woolloongabba north towards Albert Street beneath ...
More Information
An online webinar to hear first-hand from Cross River Rail’s experts about tunnelling works and how it may impact local residents and businesses.
Experts from the Cross River Rail ...
More Information
Roadheaders start tunnelling towards Boggo Road - Two 115t roadheaders have started to mine the remainder of the 870 m Cross River Rail twin tunnels between Woolloongabba and Boggo ...
More Information
TBM Else - the first of Cross River Rail’s two 1350 t TBMs in Brisbane - has been moved into position underground in the Woolloongabba site’s station cavern to commence tunnelling on the ...
More Information
Minister for Transport and Main Roads - The Honourable Mark Bailey.
Cross River Rail’s twin massive Tunnel Boring Machines (TBMs) have been named after two groundbreaking Queensland ...
More Information
The first of the two TBMs that will excavate the bulk of Cross River Rail’s 5.9km twin tunnels is passing factory acceptance testing, before being disassembled and transported by trucks to ...
More Information
Work is progressing well, across Cross River Rail’s eight worksites in Brisbane. The project will help transform South East Queensland by unlocking the bottleneck at the core of ...
More Information
Cross River Rail is boosting the Queensland Economy by $4.1 million per day, supporting a workforce of over 2,400 and providing work for more than 400 suppliers and subcontractor companies, 90% of ...
More Information
At the beginning of August two TBMs (weight 1350 t and 165 m length) arrived in Queensland, ready to be fitted out before being deployed to dig the Cross River Rail twin tunnels in early 2021. ...
More Information
Cross River Rail in Brisbane (Australia) will test underground blasting at the site of the new Albert Street underground station and the new Woolloongabba station site, in a move to speed up ...
More Information
Ghella, as part of the Pulse consortium, which is led
by CIMIC Group, has reached contractual and financial close with the State
of Queensland to deliver the Tunnel, Stations and Development (TSD) ...
More Information
The Palaszczuk Government has announced the international
consortia that have won the three major works packages for the Cross-River Rail
Project in Brisbane.
The Palaszczuk Government has ...
More Information
Cross River Rail in Brisbane is the Queensland Government’s highest priority infrastructure project. It is required to support the region’s growing urban population. With the population ...
More Information