Excavation, portal structure construction and TBM removal continues in March at the Northern Tunnel Portal site and is on track for completion in mid-2022.
Once the team reaches the required depth, concrete base slabs and inner walls will be progressively built within the structure.
Ongoing activities include waterproofing and construction of a concrete slab on top of the roof, which will be backfilled using material stockpiled on site.
For further information please click here and au/37 for tunnelbuilder archive and also visit https://crossriverrail.qld.gov.au/. 09/22.