Excavation, portal structure construction and TBM removal continues in March at the Northern Tunnel Portal site and is on track for completion in mid-2022.
Once the team reaches the required depth, concrete base slabs and inner walls will be progressively built within the structure.
Ongoing activities include waterproofing and construction of a concrete slab on top of the roof, which will be backfilled using material stockpiled on site.
For further information please click here and au/37 for tunnelbuilder archive and also visit https://crossriverrail.qld.gov.au/. 09/22.
09.05.2025 Germany
09.05.2025 Poland
09.05.2025 Switzerland
13.05.2025 Germany
14.05.2025 Switzerland
14.05.2025 Poland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Czech Republic
26.05.2025 Norway
28.05.2025 Italy
02.06.2025 Spain
04.06.2025 Norway
04.06.2025 Austria
05.06.2025 Iceland
09.06.2025 Switzerland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
24.06.2025 Switzerland
27.06.2025 Switzerland
28.07.2025 Brazil