Brisbane’s new underground making tracks - Rail tracks installation in the Brisbane's Cross River Rail’s twin tunnels commenced from just south of the future Albert Street station, and is headed towards the Brisbane River and future Woolloongabba station.
The 40-strong track installation crew will progress - around 50-100 metres a day- out the project’s 5.9-km twin tunnels with around 25 km of rail over the next 12 months, creating Brisbane’s first below-river rail crossing in the process.
Unlike surface tracks where rails are laid on top of sleepers and ballast (or rocks), rail in the tunnels is placed on concrete blocks, which are then embedded into the underlying concrete slab.
Northern Tunnel Portal construction update
Excavation and construction of the Northern Tunnel Portal structure is ongoing and due for completion in late 2022. Construction of the permanent internal walls and base slab is now underway. In the coming months, E&M services will start to be installed within the structure and tunnel via the Northern Tunnel Portal . Click here and au/37 for tunnelbuilder archive. Visit https://crossriverrail.qld.gov.au/. 26/22.
09.05.2025 Germany
09.05.2025 Poland
09.05.2025 Switzerland
13.05.2025 Germany
14.05.2025 Switzerland
14.05.2025 Poland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Czech Republic
26.05.2025 Norway
28.05.2025 Italy
02.06.2025 Spain
04.06.2025 Norway
04.06.2025 Austria
05.06.2025 Iceland
09.06.2025 Switzerland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
24.06.2025 Switzerland
27.06.2025 Switzerland
28.07.2025 Brazil