Brisbane’s new underground making tracks - Rail tracks installation in the Brisbane's Cross River Rail’s twin tunnels commenced from just south of the future Albert Street station, and is headed towards the Brisbane River and future Woolloongabba station.
The 40-strong track installation crew will progress - around 50-100 metres a day- out the project’s 5.9-km twin tunnels with around 25 km of rail over the next 12 months, creating Brisbane’s first below-river rail crossing in the process.
Unlike surface tracks where rails are laid on top of sleepers and ballast (or rocks), rail in the tunnels is placed on concrete blocks, which are then embedded into the underlying concrete slab.
Northern Tunnel Portal construction update
Excavation and construction of the Northern Tunnel Portal structure is ongoing and due for completion in late 2022. Construction of the permanent internal walls and base slab is now underway. In the coming months, E&M services will start to be installed within the structure and tunnel via the Northern Tunnel Portal . Click here and au/37 for tunnelbuilder archive. Visit https://crossriverrail.qld.gov.au/. 26/22.
30.03.2026 Italy
31.03.2026 Ireland
07.04.2026 Austria
08.04.2026 Norway
09.04.2026 France
09.04.2026 Germany
14.04.2026 United States
23.04.2026 Sweden
24.04.2026 United Kingdom
24.04.2026 Switzerland
27.04.2026 Italy
27.04.2026 Switzerland
30.04.2026 Sweden
30.04.2026 Switzerland
04.05.2026 Switzerland
04.05.2026 Slovakia
04.06.2026 Switzerland
07.07.2026 Germany
31.12.2031 Germany