The TBMs - used for excavating the Cross River Rail’s tunnel in Brisbane - have now been taken away from site, allowing the gantry crane to be removed as well: click here for the video. Construction can also start on the final section of the Northern Tunnel Portal roof that was kept open to extract the TBM components.
Delivery of railway tracks for the twin tunnels has also begun. Railway tracks for the northern section of the Cross River Rail twin tunnels will be installed via the Northern Tunnel Portal site. The final delivery of railway tracks will occur from 09/05/2022. Click here for further information and here and au/37 for tunnelbuilder archive. Visit https://crossriverrail.qld.gov.au/. 17/22.
18.11.2025 Austria
18.11.2025 Germany
20.11.2025 Romania
21.11.2025 Switzerland
21.11.2025 Austria
27.11.2025 Switzerland
27.11.2025 Spain
09.12.2025 Italy
09.12.2025 Switzerland
09.12.2025 Belgium
16.12.2025 Iceland
06.01.2026 France
23.01.2026 Switzerland