Tunnelbuilder Promoting the world's tunnelling industry to a huge qualified audience

View the Spanish Tunnelbuilder website View the Italian Tunnelbuilder website

Archive Search

United States

United States, Nevada - us/16

Lake Mead Intake

  Monumental expansion programme to meet the future water needs of Las Vegas includes a lake tap shaft to depth 76 m beneath the lake surface to be bored from a barge; an intake tunnel in jointed and faulted metamorphic rock; 22 x 1.82 m-diameter pumping shafts bored from surface to the 100 m level; and a 3.65 m-diameter subaqueous concrete pipeline. Kiewit Construction has completed the 7.6 m-diameter access shaft to the 115 m level and the 792 m East tunnel has broken through using drill/blast supported by rockbolts and shotcrete at a rate of 6 m/day. Work progressing on the 502 m intake tunnel. Zeni Drilling has completed the first shaft. March 1999.   Atlas Copco 322 twin-boom and basket drilling 3.8 m holes for 2.5 m advance in intake tunnel. Mucking out by Wagner 3.5 Scooptrams. Support by fully-grouted Ingersoll Rand C-tube rockbolts of lengths to 3.8 m and 10 cm of fibre reinforced shotctrete. Forward grouting commenced after 250 m after water inflows of 600 gal/min were encountered. 25 m probe holes have been necessary. The well shafts are being pilot drilled blind to full depth using a reverse circulation rotary drillrig and then reamed to the 1.82 m final diameter to accommodate the 1.3 m diameter pumping columns. June 1999.  Zeni reported completion of all 22 well shafts, including casing and grouting. The bases of the well shafts have been exposed by a top heading through the forebay, and the bench is now underway to complete. Breakthrough of intake tunnel into shaft scheduled for late-November, 1999 and flooding of tunnel in January, 2000. November 1999.The Southern Nevada Water Authority has awarded a USD447 million contract to Impregilo and its US subsidiary S.A. Healy to design and build the so-called third straw to draw water from the Lake Mead reservoir. This is a concrete-lined tunnel 6 m in diameter and approx. 4.8 km long underneath the bed of Lake Mead. Construction should begin before the end of the year and eventually involve a massive tunnel boring machine that will be manufactured in Germany and shipped to the United States. The third straw is slated to go on line by early 2013. Visit www.impregilo.it and www.sahealy.comThe Lake Mead reservoir on the Colorado River behind Hoover Dam supplies about 90% of the water used in and around Las Vegas, but the lake level continues to drop in the face of an eight-year drought. The new intake will allow the authority to continue drawing water even if Lake Mead shrinks below the level of the two existing straws. One or both of the existing inlet pipes would be forced to shut down if the lake level falls below current intakes. Lake Mead is currently at a surface level of about 340 metres above sea level, or about 20 metres above the 320 m level of the original intake. A second intake draws water from 305 metres above sea level. It was completed in 2002, at a cost of about USD80 million. The third intake is expected to draw water from below a 275 m elevation. 13/08.The Southern Nevada Water Authority is also soliciting bids, deadline 21st April, 2008 for the Lake Mead intake No. 2 connection and modifications project (contract No. 070F 05 C1). The proposed underground works include connection to the existing intake tunnel and modifications to the existing intake structure, including but not limited to a 6.7 m-diameter 116 m-deep shaft, a ventilated building over the top of the shaft, a 4.3 m-wide by 4.9 m-high by 82 m-long modified horse shoe tunnel from shaft to existing IPS-2 tunnel, 4.3 m-wide by 4.9 m-high by 76 m-long modified horse shoe tunnel connection to the future tunnel from intake No. 3, and existing IPS-2 intake modifications. Visit www.snwa.com/nonpvcs/construction_ops/inv/070F05C1.pdf 13/08.Further technical details are available regarding the Lake Mead intake No. 3 shafts and tunnel project, recently awarded to Vegas Tunnel Constructors, a joint venture of Impregilo and S.A. Healy. The tunnel will primarily be excavated in late Tertiary sedimentary and volcanic bedrock. Of the 4,666 m-long intake tunnel, about 300 metres will be excavated in the Saddle Island Lower Plate (amphibolites, schist, and gneiss) and about 370 metres in the Saddle Island Upper Plate (schist, amphibolites, gneiss, pegmatite, dacite intrusives). The majority of the tunnel drive (about 3,540 metres) is located in the Muddy Creek formation (conglomerate, breccias, sandstone, siltstone and gypsiferous mudstone). As the TBM approaches the intake riser, it will pass through about 370 metres of red sandstone, and the final 90 metres will be in the Callville Mesa basalt.Except for an erection chamber and starter tunnel that will be excavated by drill and blast, the tunnel will be excavated by a Herrenknecht convertible hybrid tunnel boring machine. The TBM, in open mode, will evacuate the spoils by screw conveyor feeding a continuous tunnel conveyor. The continuous tunnel conveyor will feed two muck skips that are hoisted up the intake access shaft and then moved to a stockpile on site. In closed mode, the screw conveyor is retracted from the cutterhead and the TBM functions in fully slurry mixshield mode, utilizing a separation plant. The tunnel will be supported by a precast, bolted, gasketed tunnel lining with five plus a key segments. Inside diameter will be 6.1 m, and the segment ring will be 1.83 m long. Visit www.herrenknecht.comOther underground structures include the 180 m-deep intake access shaft with cast-in-place concrete liner with inside diameter of 9 m, excavated by drill and blast. A stub tunnel approximately 26 m long will be excavated by drill and blast at depth of about 110 metres to provide a connection to the future pump station. At the bottom of the shaft will be a large TBM erection chamber, starter tunnel, and tail tunnel that will provide the Southern Nevada Water Authority (SNWA) with an option for a future tie-in and water transmission. The intake riser will be constructed in Lake Mead at a depth of 90-107 m below the lake surface. Lake-bottom excavation will be by underwater drilling and blasting. The intake riser will be constructed by sunken tube technology and will provide a docking station for the TBM.The construction manager is Parsons Water and Infrastructure. SNWA’s design engineer is MW/Hill, a joint venture of Montgomery Watson and CH2M Hill. The contractor’s design engineer is Arup USA, with Brierley Associates. Visit www.snwa.com, www.parsons.com/about/bus_unit/gbu/water, www.mwhglobal.com, www.ch2m.com, www.arup.com and www.brierleyassociates.com 15/08.



Permalink

United States, Massachusetts - us/15

MetroWest Water Supply

  Shea/Traylor/Healy well into contract 2 with 8.3 km of total 19 km of 4.93 m-diameter drive completed using Robbins TBM with CTS backup and now gearing up for contract 3A which involves another 1.34 km using roadheader and TBM. Obayashi/Modern Continental meanwhile have completed over 3.4 km of contract 6054 which comprises 7.82 km of 5 m-diameter rockbolted drive using a CTS TBM. Some 1.2 km was in hard, abrasive rock which necessitated cutter changes at a rate of one every 1.5 m of advance. March 1999.   Contract 242 by Shea/Traylor/Healy has completed 8.75 km drive west to break into shaft constructed by adjacent contractor Obayashi/Modern Continental under separate contract. The latter have advanced 5.9 km using 5.25 m-diameter CTS TBM with 2.26 km to complete. Shea/Traylor/Healy now halfway through their 11 km drive west while also mining 1.4 km TBM/roadheader drive under contract CP3A. Sept 1999.  Obayashi/Modern Continental reports mining in difficult ground through a fault zone on contract 6054 with 6.4 km of the total 8.15 km completed. Grouting with steel sets and wire mesh lagging. November 1999.At 31st October, 2001, work was well underway on the 28.6 km MetroWest water supply tunnel (MWWST). The 7.9 km western tunnel segment CP-1 from Shaft E in Southborough to the 62.8 m-deep Shaft D in Marlborough was 79% completed by the Obayashi/Modern Continental jv using a TBM. The contractor completed the excavation of the tunnel in July, 2000. From Shaft D, the MWWST will connect to the Walnut Hill water treatment plant and to the existing Cosgrove tunnel. Tunnel concrete lining operation began in December, 2000 and by end-October 2001, over 4.1 km of the tunnel has been lined which represents a 53% completion. Over the next few months, the contractor will carry on with the tunnel lining and the grouting operations in the lined section. Work on the CP-1 segment is about seven days behind schedule. Completion is expected for April, 2003. Contract value is $149.7 million. Visit www.obayashi.co.jp and www.moderncontinental.comThe 19.1 km middle tunnel segment CP-2 in Southborough, Framingham, Wayland and Weston was 84% completed by a jv of Shea, Traylor Bros., and Healy. It was tunnelled in two directions using two TBMs from the 123.7 m-deep Shaft L. The 8.5 km west heading tunnel was completed in July, 1999 with 1,280 metres lined with concrete on 31st October, 2001. The 10.6 km east heading tunnel was bored under Dudley Pond in Wayland and past the interconnections at Shafts NE and NW in Weston continues eastward to the eastern tunnel segment. It was completed in May, 2000. The contractor has currently lined 7 km, 66% complete. The raise boring excavation of Shaft NE, 4 m in diameter x 131 m-deep, was completed on 19th November, 2001. It is the last shaft on the MWWST project. Work on the CP-2 segment is on schedule for completion in April, 2003. Contract value is $254.5 million. Visit www.traylor.com and www.sahealy.com The 1.4 km eastern tunnel segment CP-3A connects the CP-2 segment with Shaft 5A, at the east end of the system, where it will connect to the existing Boston city tunnel to the south and with the 96 m-deep Shaft W and storage tanks to the north. Excavation of the tunnel was completed at spring 2000 by the same jv as CP-2. Concrete lining ended in February, 2001. Since then, 670 metres of 3.05-3.7 m pipes to connect Shaft 5A to the city tunnel is in progress. This contract will be completed in July, 2002. Value is $56.9 million. Visit www.mwra.state.ma.us/water/html/metrow.htm for a full project overview. 03/02.



Permalink

United States, Illinois - us/14

Main Sewer

  Kenny/Kiewit/Shea sinking 9.1 m x 94 m-deep working shaft and 10.6 m x 97 m-deep gate shaft and will commence 10.4 km tunnel in April, 1999 using 8.32 m Robbins TBM upsized and modified from recently-completed Des Plaines project. 2.5 km x 4.57 m second tunnel will be started later. Completion November, 2002. All part of the ongoing TARP megaproject. March 1999.   10.5 km mainline drive north underway by Kenny/Kiewit/Shea using 8.7 m-diameter refurbished Robbins hardrock TBM. Second 5.7 m-diameter Robbins working on two 1.27 km spurs, and three Lovat TBMs will be employed later. Sept 1999.   8.7 m Robbins breaking records, having achieved a best month of 1.6 km and best day of 97 m. All rock is being sold from surface plant. Second Robbins underway and first of three Lovat TBMs will start in early-2000. November 1999.   Groundbreaking ceremony took place in Calumet City for the Little Calumet Leg, a 7.9 mile (12.7 km) tunnel, 15 feet (4.6 m) in diameter, which is the last leg of the Tunnel and Reservoir Plan (TARP) or Deep Tunnel involving more than 100 miles of tunnels. Tunnel construction is to end in March 2006. Construction of TARP began in 1976. The cost of the 93 miles (150 km) of tunnel completed so far has been about $2 billion. Two reservoirs to hold billions of gallons of storm water and raw sewage still need to be built. The entire project is expected to be operational in 2014. Visit www.mwrdgc.dst.il.us/plants/tarp.htm and www.epa.gov/25water/tarp 25/02. The Jay Dee/Affholder JV started tunnelling in mid-February on the final tunnel segment of the District's Tunnel and Reservoir Plan (TARP) after months of preparatory work including the excavation of a 10.4 m-diameter 60 m-deep shaft to the tunnel level. This 12.7 km (7.9 mile) tunnel, known as the Little Calumet Leg, serves a 38.6 sq km (14.9 sq mile) area of southern Cook County preventing Combined Sewer Overflows (CSOs) from spilling into the Little Calumet River. The tunnel will be driven through limestone at a depth of approximately 46 to 91 m (150 to 300 feet) below ground through the use of a Robbins TBM. Electric motors on the TBM turn a 5,537 mm (18' 2") diameter cutting head that is steered and thrust forward by hydraulic cylinders to cut through the rock. The excavated rock is brought to the surface via conveyor belts. The $168.7 million contract was awarded in January 2002 and is scheduled for completion in March 2006. Upon completion of this segment, the TARP system will consist of a total of 176 km (109.4 miles) of tunnels. Visit www.mwrdgc.dst.il.us/default.html and www.robbinstbm.com 11/03.The Robbins Company reports record progress by Affholder on the 12.8 km-long Little Calumet leg of Chicago's 175 km-long TARP project. Their 5.56 m-diameter TBM is driving the CSO tunnel in two sections from a 60 m-deep central launch shaft through limestone with a compressive strength of 83-96 Mpa. The Robbins TBM Model 1410-251-2 has seven 450 hp (335.6 kW) motors driving the cutter head, which is fitted with 39 wedgelock 19 in (483 mm) cutters. Best advances: 45.75 m/8h shift; 116.7 m/day; and 474.7 m/week. Most rock excavated in 24 h is 2,836.55 cu m. Robbins supplied the TBM, back up, extensible main conveyor, vertical shaft conveyor, surface conveyor, and stacker. More from robyj@robbinstbm.com or visit www.robbinstbm.com 22/03.



Permalink

United States, California - us/13

San Ramon Sanitary Conveyance

5,000 ft tunnel through soft sedimentary rocks at Dougherty Valley to carry 1.5 m-diameter pipeline and twin 0.3 m-diameter bypass lines. Shaft at one end and portal at the other. Under design by URS Greiner Woodward Clyde for Central Costa Sanitary District, Martinez, CA. April 1999.



Permalink

United States, California - us/12

Riverside Bad Lands Water Supply

Shank/Balfour Beatty to commence 12.7 km tunnel in June, 1999 using own-design 4.85 m TBM. Alignment mainly below water table at average depth of 60 m in alluvium and fractured metamorphic rock. Two intermediate shafts required for ventilation and grout transport. Probehole drilling, grouting and dewatering expected to stem water inflow and improve ground conditions. Part of Inland Feeder project. Completion scheduled September, 2002. March 1999.  See Inland Feeder us/23 for further updates. Sept 1999.



Permalink

United States, California - us/11

San Bernardino TBM

Shank/Balfour Beatty driving 9,286 m-long Arrowhead East aqueduct as part of Inland Feeder project which will require a total of 29 km of tunnels. 5.38 m shielded TBM designed by contractor launched March, 1998 and is working in granite and gneiss erecting 1.2 m-deep rings of four precast segments. Average advance on single-shift working is 18 rings/day with 28 rings maximum. 2 km completed to date. Steel-encased 12 ft internal diameter concrete pipe will be installed later and backgrouted in place. March 1999.  See Inland Feeder us/23 for further updates. Sept 1999.



Permalink

Uruguay

Uruguay, Montevideo - uy/11

Metro

Proposal for $900 million metro system of four separate lines to be built over four years. Concession to build and operate sought from municipal administration by private sector consortium. Three of the proposed lines are mainly underground. August 1998.  Officials have travelled to Bilbao to visit the metro in the Basque city. The project includes three underground lines and a surface light rail line. US$60 million first stage includes construction of the Red Line from the harbour to Ejido, where it would connect with the Blue Line. The 15 km line would serve Parque Rodí³, Punta Carretas, and Pocitos. Second stage is extending the Red Line to Estadio Centenario and Hospital de Clí­nicas. Third stage is a further extension to Punta Rieles and the beginning of the Yellow Line from Tres Cruces to Hipí³lito Irigoyen. Then the line will run parallel to Avenida Italia. French company Bceom, RATP and Alstom have already been approached in the past. Total investment of US$900 million. 20/02.



Permalink

Venezuela

Venezuela, Aragua and Miranda States - ve/19

Railway

Venezuela's state railway autonomous institute IAFE and the Italian embassy signed in January a letter of intent for the construction of the 70 km-long La Encrucijada-Charallave railway section, the last link to connect Caracas with Puerto Cabello. The path is in phase of optimisation and for the moment 18 tunnels stretching for a total of approx. 25 km are planned. The letter of intent sets the basis for awarding the contract to a consortium of builders which is expected to be formed by Ghella, Astaldi and Impregilo, who are currently building the Puerto Cabello-La Encrucijada section. Click here. 08/08.



Permalink

Venezuela, Los Llanos Region - ve/18

Railway

Astaldi, in joint venture with Impregilo and Ghella, is to build two new railway lines in Venezuela valuing a total of USD2.2 billion. The two new lines are San Juan de los Morros-Dos Caminos-Calabozo-San Fernando de Apure (252 km) and Chaguaramas-Las Mercedes-Cabruta (201 km). The works are part of intergovernmental agreements between Italy and Venezuela. The joint venture, in which each member holds equal 33.33% stakes, will carry out the works for the two railway sections over the course of 76 months. Start-up is planned for the second quarter of 2006, immediately after the contracts are signed. The project, which is aimed at fostering the development of Venezuela's central and southern area, involves building 453 km of new railway lines, 15 km of which in tunnel and with 12 km of bridges and viaducts. The project also includes designing and installing superstructure, 13 railway stations, three logistic centres, and a maintenance workshop. In addition to the value of the works to build the lines, there will also be USD1 billion in options for designing, supplying and assembling railway systems (signals, control, telecommunications, electrification and rolling stock). Visit www.astaldi.com, www.impregilo.it, www.ghellagroup.com and www.infraestructura.gov.ve 16/06.The joint venture between Astaldi, Ghella and Impregilo has signed its two contracts worth a total of USD2.2 billion with Venezuela's autonomous state railways (IAFE). The signing of the contracts follows intergovernmental agreements reached in April between Italy and Venezuela. The contracts concern the construction of the new San Juan de los Morros-San Fernando de Apure (252 km) and Chaguaramas-Cabruta (201 km) railway lines. These 453 kilometres of new lines involve 15 km of tunnels and 12 km of bridges and viaducts. Visit www.astaldi.com, www.impregilo.it, www.ghellagroup.com and www.infraestructura.gov.ve 25/06.GEI, a consortium formed by Astaldi, Ghella and Impregilo will be responsible for the construction of the 251 km San Juan de los Morros-San Fernando de Apure rail line, whereof 41 km in the mountain and 210 km in plain. The line totals a cost of USD1.6 billion. The contract has been signed and the site is being prepared. It is a design/build contract. At this stage, the project is in the design phase so that many of the technical aspects will have to be defined in the future, once the project is finalised. From the operational point of view, the planning and organisation of the project is underway and soon the sites will be prepared and mobilised.This line has been divided in lots, the construction of which will be undertaken by the contractors who teamed to form the consortium GEI. According to the preliminary project, ten single bored tunnels will be constructed for a total of 16 km. The cross section is 90 sq m. There are no other underground structures (stations, shafts, etc.). Geology consists of metamorphic rock (micaschists).Ghella will build the 6.3 km San Juan tunnel (from chainage 2+300 to chainage 8+600), which is part of subsection D1-G which goes from chainage 0+000 to 11+611, to be also fully built by Ghella. The other tunnels on the line are part of the subsections awarded to Impregilo and Astaldi (see pdf here of how the tunnels are divided and pdf here of the division into lots). Visit www.ghellagroup.com, www.astaldi.com and www.impregilo.itThe planned tunnelling method is to use hydraulic breakers where possible (FIAT Kobelco excavators and Krupp and Indeco hammers) and drilling and blasting with Atlas Copco jumbo drill rigs, Cat and FIAT Kobelco loaders, and Astra trucks. There will be six working faces. Visit www.fiatkobelco.com, www.indeco-breakers.com, www.atlascopco.com, www.cat.com and www.astraspa.comFor support, Swellex bolts, three CIFA shotcrete pumps and three Scamac shotcrete pumps will be used. The shotcrete will be reinforced with Maccaferri fibres. Visit www.swellex.com, www.cifa.com, www.scamac.com and www.maccaferri.comFor mucking-out, 12 Cat 966 loaders, FIAT Kobelco loaders and 24 Astra trucks will be used in addition to Dieci telescopic elevators. Visit www.dieci.com 48/06.



Permalink

Venezuela, Caracas - ve/17

Metro Line 3

  Construction of the El Valle-La Rinconada section on Line 3 will commence first quarter of 2002. Four TBMs to be used, two of which coming from Line 4 once the twin tunnels between Capuchinos and Plaza Venezuela are completed. Visit www.metrodecaracas.com.ve 52/01. Odebrecht signed a contract to extend southwards Line 3 from El Valle to La Rinconada serving four stations in Los Jardines, Coche, Mercado and La Rinconada where the line will intersect with the Valles del Tuy railway. Completion scheduled for 2006. Visit www.metrodecaracas.com.ve and www.odebrecht.com.br 38/02.



Permalink