Shea/Traylor/Healy well into contract 2 with 8.3 km of total 19 km of 4.93 m-diameter drive completed using Robbins TBM with CTS backup and now gearing up for contract 3A which involves another 1.34 km using roadheader and TBM. Obayashi/Modern Continental meanwhile have completed over 3.4 km of contract 6054 which comprises 7.82 km of 5 m-diameter rockbolted drive using a CTS TBM. Some 1.2 km was in hard, abrasive rock which necessitated cutter changes at a rate of one every 1.5 m of advance. March 1999.
Contract 242 by Shea/Traylor/Healy has completed 8.75 km drive west to break into shaft constructed by adjacent contractor Obayashi/Modern Continental under separate contract. The latter have advanced 5.9 km using 5.25 m-diameter CTS TBM with 2.26 km to complete. Shea/Traylor/Healy now halfway through their 11 km drive west while also mining 1.4 km TBM/roadheader drive under contract CP3A. Sept 1999.