On 13.02.2018 the second TBM, launched from Dateo Station on 05.01.2018, has completed the last underground section from Linate airport to Tricolore Place on the East section of M4 line at Milan.
More than 5 km have been driven with the installation of over 7000 concrete rings for the lining of both the tubes. Which means 40% has been completed for the M4 line.
Next summer two TBMs will begin to drive the west section from San Cristoforo to Solari station. Click here for a video, here and it/16 for tunnelbuilder archive. Visit http://www.metro4milano.it. 07/18.
09.05.2025 Germany
09.05.2025 Poland
09.05.2025 Switzerland
13.05.2025 Germany
14.05.2025 Switzerland
14.05.2025 Poland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Czech Republic
26.05.2025 Norway
28.05.2025 Italy
02.06.2025 Spain
04.06.2025 Norway
04.06.2025 Austria
05.06.2025 Iceland
09.06.2025 Switzerland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
24.06.2025 Switzerland
27.06.2025 Switzerland
28.07.2025 Brazil