On 13.02.2018 the second TBM, launched from Dateo Station on 05.01.2018, has completed the last underground section from Linate airport to Tricolore Place on the East section of M4 line at Milan.
More than 5 km have been driven with the installation of over 7000 concrete rings for the lining of both the tubes. Which means 40% has been completed for the M4 line.
Next summer two TBMs will begin to drive the west section from San Cristoforo to Solari station. Click here for a video, here and it/16 for tunnelbuilder archive. Visit http://www.metro4milano.it. 07/18.
01.07.2025 Germany
01.07.2025 Poland
03.07.2025 Czech Republic
04.07.2025 Norway
10.07.2025 Germany
15.07.2025 Spain
22.07.2025 France
28.07.2025 Austria
28.07.2025 Brazil
29.07.2025 Czech Republic
29.07.2025 Germany
31.07.2025 France
11.08.2025 Switzerland
14.08.2025 Switzerland
19.08.2025 Spain
01.09.2025 Brazil
01.09.2025 Switzerland
15.09.2025 Sweden