Renny, the last West End Connectors’s TBM on the Eglinton Crosstown West Extension (ECWE) project, has officially completed its 6.3-km journey from Renforth Drive to the extraction shaft, ...
More Information
Press release - One of two twin tunnel boring machines digging the western underground segment of the Eglinton Crosstown West Extension has broken through the final ...
More Information
The Eglinton Crosstown West Extension project at Toronto has hit two major milestones - Rexy, one of the TBMs has completed 6 kms of tunnelling so far. The other TBM, Renny, has completed just over ...
More Information
Last week the Eglinton Crosstown West Extension reached another milestone: Renny, the first TBM to start tunnelling passed the halfway point, digging over 3 km of the roughly 6 km ...
More Information
In the last six months Renny, the first TBM to start tunnelling between Renforth Drive and Scarlett Road for the contractor West End Connectors Construction (WECC) has tunnelled 1.9 km, while Rexy, ...
More Information
Metrolinx reached another milestone for the Eglinton Crosstown West Extension with the second TBM, named Rexy, starting the journey from Renforth Drive to Scarlett Road. The second tunnel for the ...
More Information
On the 11/04/2022 Metrolinx marked a major milestone as tunnelling began on the Eglinton Crosstown West Extension, the 9.2-km extension of the Eglinton Crosstown LRT from Mount Dennis Station to ...
More Information
After thousands of votes from the community, the winning names are in for the Scarborough Subway Extension’s TBM and the two machines that will build the Eglinton Crosstown West ...
More Information
The TBMs, which will dig the tunnels for the Scarborough Subway Extension and the Eglinton Crosstown West Extension in Toronto, arrived at the ports of Oshawa and Hamilton in mid-December 2021. ...
More Information
On 19/10/2021 Metrolinx introduced their naming contest for the 3 giant machines that will dig the tunnels for the Eglinton Crosstown West Extension and Scarborough Subway Extension in the Greater ...
More Information
Infrastructure Ontario and Metrolinx have identified Strabag and West End Connectors as the First Negotiations Proponents (FNPs) to design, build and finance the tunnels for the Scarborough ...
More Information
Infrastructure Ontario (IO) and Metrolinx have issued two Request for Proposals (RFPs) to teams who have recently been shortlisted to bid on the advance tunnelling work on the Scarborough Subway ...
More Information
Infrastructure Ontario (IO) and Metrolinx have shortlisted six teams for advance tunnelling work on the Scarborough Subway Extension and the Eglinton Crosstown West Extension projects. ...
More Information
Infrastructure Ontario (IO) and Metrolinx have issued two Requests for Qualifications (RFQs) for advance tunnelling work on the Scarborough Subway Extension and the Eglinton Crosstown West Extension ...
More Information