On the 11/04/2022 Metrolinx marked a major milestone as tunnelling began on the Eglinton Crosstown West Extension, the 9.2-km extension of the Eglinton Crosstown LRT from Mount Dennis Station to Renforth Drive.
Over the next 20 months, the two massive TBMs Rexy and Renny will work 20 m below ground, digging twin tunnels that will stretch over 6 km in length , forming a large part of the Eglinton Crosstown West Extension, which will expand the soon-to-be-completed Eglinton Crosstown LRT.
The two TBMs will start digging from the launch site near Renforth Drive and Eglinton Avenue West, moving 10 to 15 m a day as they travel east to Scarlett Road, where they will be pulled out of the ground.
Renny, the first TBM to start digging the tunnels, will be followed by TBM Rexy about a month later. For more information click here and ca/39 for tunnelbuilder archive. Visit https://blog.metrolinx.com/. 15/22.