The east tube of the Morazzone rock tunnel (GN71) is 2,089.7 m-long from P.K. 2+899.00 to P.K. 0+809.30. The tunnel is excavated from two sides: at north adit in Lozza municipality with drill/blast and at south adit in Gazzada-Schianno municipality with hammer. By May, 2013 advance from south was 214.3 m (pk 1+023.7 – site 25). Better ground conditions after pk 1+005 allowed consolidation with VTR and steel pipes (site 24) and steel pipes (site 25) instead of jet grouting. The advance from north adit was 770.20 m (pk 2+128.8).
The west tube of the tunnel (GN72) is 2,090.00 m-long from P.K. 2+896.00 to P.K. 0+806.00. By May the advance from South adit was 164.5 m (pk 0+970.5 – site 19). The consolidation method used is C1 (jet grouting). The advance from north adit was 735.3 m (pk 2+160.7). Click here for some photos, here and it/128 for tunnelbuilder archive. Visit www.pedemontana.com. 23/13.
09.05.2025 Germany
09.05.2025 Poland
09.05.2025 Switzerland
13.05.2025 Germany
14.05.2025 Switzerland
14.05.2025 Poland
16.05.2025 Switzerland
16.05.2025 Italy
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Czech Republic
26.05.2025 Norway
28.05.2025 Italy
02.06.2025 Spain
04.06.2025 Norway
04.06.2025 Austria
05.06.2025 Iceland
09.06.2025 Switzerland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
24.06.2025 Switzerland
27.06.2025 Switzerland
28.07.2025 Brazil