November 21, 2023, marked a pivotal moment as RFI and Webuild signed a Contract Rider valued at EUR 700 million. This agreement aims to ensure the seamless progression of the Terzo Valico dei ...
More Information
On the 04/12/2022 - celebrating Saint Barbara the patron saint of miners and tunnellers - there was a breakthrough between Polcevera and Cravasco work site in the Valico tunnel (odd track). This ...
More Information
On 21/12/21 the excavation activities for the new San Tomaso tunnel, a strategic part of the Terzo Valico dei Giovi – Genoa Junction One Project, and the first of the Genoa railway junction, ...
More Information
The Terzo Valico dei Giovi-Nodo di Genova project has reached another milestone only 6 months after a breakthrough along the planned Valico Tunnel, which will become the longest railway tunnel in ...
More Information
The Fegino construction site has had a new breakthrough between the Voltri interconnection tunnel (the so-called “odd-numbered” track) and a large structure in the already completed ...
More Information
On 17/06/2021 another milestone was reached on the Terzo Valico dei Giovi project. This project was commissioned by Rete Ferroviaria Italiana (RFI) (Gruppo FS Italiane) and had its first ...
More Information
On 16/04/2021 at the Libarna site, near the municipality of Arquata (AL) there was a breakthrough inside a chamber of the Serravalle tunnel, the second longest tunnel for the Terzo Valico dei ...
More Information
On 22.10.2015 Cipa Spa, along with the contractor COCIV, finished the excavation of the 278 m Chiaravagna tunnel. The tunnel is part of the new high speed, high capacity railway line ...
More Information
Terzo Valico high-speed line restartsA contract agreement, value EUR500 million, has been reached between RFI and Consortium COCIV, headed by Impregilo, to restart work on lot 1 of the Terzo Valico ...
More Information
Milan-Genoa Terzo Valico startupOn 18.11.2010 CIPE approved the start of Lot 1 construction work for the dei Giovi tunnel on the Milan-Genoa high-speed line and allocated EUR700 million to the ...
More Information