The TBM Angeli being used for the Regional Connector
resurfaced on the 08 Dec 2017 at the future Grand Avenue Arts/Bunker Hill
Station. The TBM began digging the second tunnel on the project in late
September and travelled approximately 1,340 m (4,400 feet) from Little Tokyo to
reach the deepest station on the alignment.
A lot was learned from building the first tunnel which has
been used to dramatically increase the rate of production on this tunnel.
Typically, TBMs will travel 18.29 m (60 feet) to 30.48 m (100 feet) per day
when working in similar soil conditions. This TBM, however, travelled a maximum
of 57.91 m (190 feet) in a single day and averaged more than 122 m (400 feet)
per week. Crews have erected 739 precast concrete rings to build the tunnel so
far.
The TBM is now being walked across the station and
re-launched at the west end. To complete the second tunnel, the TBM will need
to dig through another 417.58 m (1,370 feet) of soil to reach the extraction
point at the intersection of 4th and Flower streets in January.
The project is forecast to be completed by December 2021.