Eiffage Genie Civil on Wednesday, August 28th at 4:30 PM - after 18 months of intensive excavation - achieved the first breakthrough in the Bjonnas tunnel (2540 m) on the E18 Langangen - Rugtvedt project, Lot 2, in Norway. The excavation was completed using explosives for the northern tube of the (2 x 2.5 km) Bjonnas twin-tube tunnel: 1,620 m excavated from Lanner (east access) and 920 m excavated from Herregarsbekken (west access). The average progress was 5 to 7 m per day per tube, depending on how many ground injection phases there were.
By the end of September, the excavation of the southern tube will be completed after the remaining 200 m are dug. Click here and no/247 for the tunnelbuilder archive. For further information visit https://www.eiffage.com. 36/24.
09.03.2026 Italy
11.03.2026 Italy
19.03.2026 Bulgaria
20.03.2026 Italy
24.03.2026 Italy
31.03.2026 Ireland
23.04.2026 Sweden
24.04.2026 United Kingdom
04.05.2026 Switzerland
04.06.2026 Switzerland