Eiffage Genie Civil on Wednesday, August 28th at 4:30 PM - after 18 months of intensive excavation - achieved the first breakthrough in the Bjonnas tunnel (2540 m) on the E18 Langangen - Rugtvedt project, Lot 2, in Norway. The excavation was completed using explosives for the northern tube of the (2 x 2.5 km) Bjonnas twin-tube tunnel: 1,620 m excavated from Lanner (east access) and 920 m excavated from Herregarsbekken (west access). The average progress was 5 to 7 m per day per tube, depending on how many ground injection phases there were.
By the end of September, the excavation of the southern tube will be completed after the remaining 200 m are dug. Click here and no/247 for the tunnelbuilder archive. For further information visit https://www.eiffage.com. 36/24.
09.12.2025 Austria
09.12.2025 Belgium
09.12.2025 Italy
09.12.2025 Switzerland
10.12.2025 Belgium
16.12.2025 Iceland
17.12.2025 Italy
06.01.2026 France
12.01.2026 Austria
23.01.2026 Switzerland