E18 Langangen - Rugtvedt is part of the E18 Langangen - Grimstad section. The project is 17 km long and has a contract value of about EUR516,47 million (NOK 5.2 billion), excluding VAT.
The project includes user structures totalling 1.6 km and 6.6 km with tunnels. In the spring of 2019, Nye Veier decided to cancel the competition for the project, which then included E18 Kjorholt - Rugtvedt due to lack of competition. Now this is scaled up, and thus extends from Langangen to Rugtvedt in Porsgrunn municipality.
The E18 Kjorholt - Rugtvedt section includes the newly excavated tunnels Kjorholt (2 200m) and Bamble (750 m) to be completed and equipped. The E18 Langangen - Kjorholt section includes the twin tube tunnels Blafjell (350 m), Bjonnas (2 250 m), Prestas (2 900 m), Brattas (400 m) and the monotube Steinbrekka (200 m) tunnel.
The following groups will compete for the contract:
EIFFAGE Génie Civil: - EIFFAGE Infrastructures, AFRY ÅF Engineering AS, Greisch Ingénierie
Arbeidsfellesskap:- Acciona Construcción, S.A.. Salini Impregilo S.p.A. ,
Rambøll Norge AS, med forpliktede selskaper:- Ramboll Danmark A/S, Ramboll Finland Oy, Ramboll Sweden AB, Ramboll UK Limited, Ingeniería Especializada Obra Civil E Industrial, S.A., HCE Construzioni S.p.A.
Arbeidsfellesskap:- Obrascón Huarte Lain, S.A., SK Engineering and Construction Co. Ltd.
COWI AS, med forpliktet selskap:- COWI A/S
FCC Construcción, S.A. - Sweco Norge AS - MC2 Estudio de Ingeniería, S.L.U.
AF Gruppen Norge AS - Norconsult AS, med forpliktet selskap, Leonhardt, Andrä und Partner Beratende Ingenieure VBI AG
For further information on the project click no/247 for tunnelbuilder the tender archive and visit https://www.nyeveier.no and https://kommunikasjon.ntb.no. 08/20.