China Railway Tunnel Group Co secured the following three contracts for the Nacka project (Sickla - Jarla - Nacka extension) for the Blue metro line, Stockholm:
• EUR7.51 million (SEK82.12 million) contract (n. 87131) for the construction of the access tunnel Sickla Värmdövägen, ref.n. FUT 2018-0164;
• EUR9.02 million (SEK98.63 million) contract (n. 87132) for the construction of the access tunnel Järla Östra, Nacka project, ref.n. FUT 2018-0165;
• EUR7.03 million (SEK76.85 million) contract (n. 87133) for the construction of the access tunnel Nacka Skönviksvägen, Nacka project, ref.n. FUT 2018-0475.
Implenia Sverige AB secured the EUR21.57 million (SEK 235.68 million) contract (n. 7713) for the construction of the Access tunnel London viadukten, Södermalm project, ref.n. FUT 2018-0460.
SBT Sverige AB 20 secured the EUR16.44 million (SEK179.70 million) contract (n. 7714) for the construction of the Access tunnel Hammarby fabriksväg, Södermalm project, ref.n. FUT 2018-0323
SBT Sverige AB 20 secured the EUR16.88 million (SEK184.50 million) contract (n. 9714) for the construction of the Access tunnel Sundstabacken, Söderort project, ref.n. FUT 2018-0162
Implenia Sverige AB secured the EUR14.22 million (SEK155.44 million) contract (n. 3715) for the costruction of the Access tunnel Södra Hagalund, Arenastaden project, ref.n. FUT 2018-0406;
For tender information please click here. 15/20.