NCC Norge AS at Oslo secured the EUR18.9 million contract,
excluding VAT, for the E39 Rogfast - contract E13, including engineering design
and construction of a side tunnel with 2 sections side by side of 1,980 m in
Arsvegen. The side tunnel will be used for transportation during the contract
of the E04 which involves construction
of the Boknafjord tunnel (27 km) towards Kvitsoy. The side tunnel, during the
operation, will be used as a ventilation tunnel. Contact the Norwegian Public
Roads Administration, Western Region, att.n Svein Tore Drevsjo, Leikanger, tel +47 90247929, email svein.drevsjo@vegvesen.no. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=495220-2017
and https://www.vegvesen.no/en/roads/Roads+and+bridges/Road+projects/e39coastalhighwayroute/news/first-tunnel-contract-signed-for-rogfast.
Ref. n. 17/92218. 01/18.