Construction will soon begin in Sydney on Metro West, with 7 station locations confirmed at Westmead, Parramatta, Sydney Olympic Park, North Strathfield, Burwood North, Five Dock and the Bays ...
More Information
Sydney’s new twin metro railway tunnels are now 70% complete as tunnelling reaches the heart of the city deep under Martin Place. TBM Nancy has arrived at the new Martin Place Station, 28 m ...
More Information
Tunnel boring machine (TBM) Mabel has broken through a wall of rock into the new Victoria Cross Station in North Sydney.
Mabel has excavated about 450,000 tonnes of sandstone and shale – ...
More Information
A second mega boring machine has arrived deep under the Sydney central business district at the new Pitt Street metro railway station. Tunnel Boring Machine (TBM) Mum Shirl started digging from ...
More Information
On August the 16th TBM Nancy broke through a wall
of rock at the site of the future Pitt Street Station, about 20m below the
heart of Sydney’s CBD. Nancy had clocked up 6km of tunnelling ...
More Information
Tunnel Boring Machine (TBM) Kathleen has passed its final
inspection and is now ready to launch from Barangaroo next month to dig the
historic rail crossing deep under Sydney Harbour.
The 975 ...
More Information
Sydney Metro’s second mega boring machine has made history, breaking through a wall of rock at the new Waterloo Station. TBM Mum Shirl started digging from Marrickville on 5 November 2018 and ...
More Information
The fourth of five mega tunnel boring machines (TBMs) has started tunnelling under Sydney.
TBM Mabel has been launched at Chatswood to help deliver 31km of tunnels between Marrickville and ...
More Information
On the 16.01.2019 Sydney Metro’s third mega TBM started digging the 6.2 km of tunnel from Chatswood to the edge of Sydney Harbour at Blues Point. This marks the next stage in delivering the ...
More Information
On the 12.11.2018 the second of five mega TBMs started tunnelling underneath Sydney. The TBM, named ‘Mum Shirl’, has been launched at the Marrickville site to help bore 31km of tunnels ...
More Information
The first of five mega TBMs has arrived to extend Sydney’s new metro railway deep under the city centre. The TBM arrived at the Marrickville launch site in eight shipping containers and 23 ...
More Information
The first of five double-shield TBMs which will deliver the
next stage of the Metro is on its way to start digging deep under Sydney on
Australia’s biggest public transport project. The TBM ...
More Information
The first of five mega TBMS designed, built and to be delivered by Herrenknecht, will be in the ground before the end of this year to drive the twin 15.5km metro rail tunnels between Chatswood and ...
More Information
The Sydney Metro project is a 66km long standalone fully automated railway system with 31 metro stations between Rouse Hill and Bankstow which has been split into two stages.
Stage 1 – ...
More Information