The Snowy 2.0 pumped-hydro megaproject has marked a significant milestone, with one of three TBMs, Lady Eileen Hudson, now two-thirds of the way through its second tunnel excavation.
The TBM is ...
More Information
On October 14th, a significant achievement was made in the Snowy 2.0 project with the breakthrough of the 216-meter tunnel connecting the water intake at the upper Tantangara reservoir to the gate ...
More Information
A new tunnel boring machine will be deployed to help keep Snowy 2.0 on its delivery timeline, subject to approval by the NSW Department of Planning, Housing and Infrastructure.
New ground testing ...
More Information
On 23 May 2024 the single shield hard rock TBM, manufactured by CREG and named Caucasus, completed the excavation of the 9 km tunnel, connecting the village of Kvesheti with the village of Kobiin, ...
More Information
Another major achievement for the Snowy 2.0 pumped-hydro project, breaking through the final three meters of the 223-m long transformer hall cavern crown. When completed, the transformer hall and ...
More Information
Tunnelling of the Snowy 2.0 headrace adit at Tantangara has restarted after a delay caused by soft ground conditions and the emergence of a sinkhole above TBM Florence.
The NSW government ...
More Information
Snowy 2.0 is being engineered to deliver clean and reliable energy storage and generation for the next 150 years. The target date for commercial operation of all units is December 2028, with first ...
More Information
July marked an exciting milestone for Snowy Hydro, Snowy 2.0 and Future Generation Joint Venture - FGJV with the relaunch of TBM Lady Eileen Hudson - one of the mega project's three TBMs - at ...
More Information
The Snowy 2.0 pumped-hydro mega project has achieved another important construction milestone, with a second tunnel excavation completed at Lobs Hole in the Snowy Mountains.
The 2.93-km ...
More Information
Construction of Snowy 2.0 - a critically important, pumped-hydro expansion of the Snowy Scheme in Australia, continues to make progress across multiple worksites. The project involves linking two ...
More Information
Press release – BAUMA, the 33rd Edition of the World's Leading Trade Fair for Construction Machinery, Building Material Machines, Mining Machines, Construction Vehicles and Construction ...
More Information
Main access tunnel - On 11th October 2022 teams from Snowy Hydro and contractor Future Generation Joint Venture celebrated the completion of the excavation of its first tunnel for ...
More Information
Lobs Hole - The TBM Lady Eileen Hudson has now excavated 2.2km of the main access tunnel, with 600 m remaining to reach the northern end of the power station complex. Once complete, the TBM ...
More Information
Snowy Hydro, the main contractor for the Future Generation Joint Venture and members of the local community celebrated the commissioning of the third and final TBM for Snowy 2.0, with a ...
More Information
This month Snowy Hydro achieved another exciting milestone, with the commissioning of Kirsten, the second of three TBMs that will excavate more than 27km of tunnels for Snowy 2.0 pumped-storage ...
More Information
Over the weekend Snowy Hydro and the principal contractor and factory operator Future Generation Joint Venture officially launched the new Snowy 2.0 precast factory in Cooma, where 130,000 concrete ...
More Information
Following a brief pause in July to install the remaining gantries and connect the conveyor belt, Lady Eileen - the first TBM to start tunnelling - is now more than 160 m into the mountain. By ...
More Information
It's winter in the Snowy Mountains and activity is hotting up at the Snowy 2.0 construction sites!
There's already more than 1,000 people working on the massive pumped-hydro project ...
More Information
On 19/03/2021 the Future Generation joint-venture, composed of the Italian company Webuild (leader), the Australian-based Clough and US-based Lane Construction- celebrated with Snowy Hydro Ltd the ...
More Information
Throughout the beginning November a huge 750-t crane has been lowering into place the giant front shield parts of the first of the three Snowy 2.0 TBMs. Snowy 2.0 is the largest renewable energy ...
More Information
The most sophisticated TBM for the construction of Snowy 2.0, the biggest renewable energy project in Australia, has passed the Factory Acceptance Test (FAT), making it ready to be shipped to the ...
More Information
Since the days of our pioneering past, we’ve grown and today we’re looking forward as we take on the energy challenges of tomorrow.
Snowy Hydro operates the Snowy Mountains Scheme, ...
More Information