Lobs Hole - The TBM Lady Eileen Hudson has now excavated 2.2km of the main access tunnel, with 600 m remaining to reach the northern end of the power station complex. Once complete, the TBM will be disassembled, extracted and reassembled at Talbingo. The supporting services will also need to be reassembled and recommissioned, ahead of Lady Eileen’s next mission to excavate the 6km tailrace tunnel heading east from Talbingo to the power station.
Also at Lobs Hole, TBM Kirsten is gaining momentum, with approximately 800 metres of the emergency cable and ventilation tunnel excavated. This tunnel is parallel to the main access tunnel and passes the southern end of the power station complex. Once past the power station, at 2.9km, Kirsten will be modified to begin uphill excavation for the inclined pressure shaft.
Tantangara - TBM Florence is now fully commissioned and has tunnelled several hundred metres west to Marica, where it will eventually meet up with TBM Kirsten. The headrace tunnel has a straight alignment and a 0.5% downhill gradient under the Gooandra plateau. This 15km tunnel is expected to take about 3.5 years to complete.
For further information click here and au/38 for the tunnelbuilder archive. Visit https://www.snowyhydro.com.au/. 24/22.
31.03.2025 Sweden
01.04.2025 Germany
01.04.2025 Poland
02.04.2025 Austria
04.04.2025 Austria
07.04.2025 France
07.04.2025 Germany
07.04.2025 Spain
08.04.2025 Netherlands
11.04.2025 Italy
11.04.2025 Switzerland
14.04.2025 Switzerland
14.04.2025 Austria
22.04.2025 Germany
22.04.2025 Sweden
23.04.2025 Norway
24.04.2025 Romania
25.04.2025 Poland
25.04.2025 Norway
25.04.2025 Switzerland
30.04.2025 Austria
06.05.2025 Germany
09.05.2025 Switzerland
14.05.2025 Switzerland
16.05.2025 Switzerland
27.06.2025 Switzerland