Slovenia, Karavanke-Obrezje - si/16

Motorway

Procurement notice for civil works for construction of section Šentvid-Koseze on motorway A2 Karavanke-Pbrezje, including the 2,148 m Šentvid tunnel. Difficult construction is anticipated in the first 100 metres in the region of the Celovška road with a minimal cover. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=55441-2003, OJ S 64, or contact Mr. Joze Jenko, Head of Procurement Dept, ZIL Engineering, Kersnikova 10, Ljubljana, Slovenia. Tel. +386 41729636. Visit www.dars.si 15/03. General procurement notice for civil works for section Sentvid-Koseze on motorway A2 Karavanke-Obrezje, including the 2,148 m Sentvid tunnel. First 200 m in cut-and-cover already completed. NATM to be used. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=114360-2003, OJ S 128, or contact Mr. Joze Jenko, Head of Procurement Dept, ZIL Engineering, Kersnikova 10, Ljubljana, Slovenia. Fax +386 1 4304580. Visit www.dars.si 29/03.Open call for bids, deadline 4th August, 2004 for construction of the 1,100 m Sentvid tunnel. It is a two- and three-lane tunnel, cross sections 95 sq m to 140 sq m. Also a 350 sq m cavern. The main rock mass type according to NATM standards is C2 and C3. NATM to be used for construction. Construction cost: SIT13 million (without VAT). Construction to start in October 2004 for completion in December 2006. Visit http://ted.publications.eu.int/udl?request=Seek-Deliver&language=en&docid=101160-2004, OJ S 120, or contact DARS, Ljubljana, fax +386 14304580. E-mail karel.licen@zilinzeniring.si, milan.crepinsek@zilinzeniring.si or sasa.kos@zilinzeniring.si 28/04.SCT and Primorje secured a SIT9.6 billion contract to build the Sentvid-Koseze section on highway A2 between Karavanke and Obrezje, including the 2 x 1,209 m Sentvid tunnel. The tunnel starts with two lanes from the north side and at about the middle of the length, it may widen to three lanes (this has yet to be decided) until the south entrance. Work has already started from the north entrance, using drill/blast to drive through stone. To date, 120 m has been excavated. Visit www.sct.si and www.primorje.si 15/05.IRGO Consulting and Geoinzeniring secured a SIT268.1 million contract for geological and geotechnical monitoring of the ground movements, the pressure between the ground and the primary lining and in the primary lining itself, and the rock mass displacements as well as geological logging at the tunnel face during construction of the Sentvid tunnel. Visit www.i-rgo.si and www.geo-inz.si 15/05.Invitation to tender, deadline 16.12.2008, for reconstruction of 257 m-long Ljubno tunnel and installation of signals and video surveillance cameras as part of EUR20 million refurbishment of 2.6 km length of A2 highway. Contract duration 20 months. Contact Sektor za razpise, Ljubljana, tel +386 1 3068204, e-mail sasa.stanesic@ddc.si 45/08. http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=287466-2008 45/08.



Permalink

Open invitation to tender, deadline 13.02.2018 for the construction of the second tube (East tube) of the 8km Karavanke/Karawanken tunnel linking Slovenian A2 and Austrian A11 motorways. The duration of the contract is 60 months. Access to the procurement documents is restricted. Further information from https://www.enarocanje.si/App/Datoteke/234179/objavljena_RD_000209-2017.zip. Contact Dars, attn Metka Celestina Cesnovar, Celie, tel +386 13009959, fax

+386 13009929, email metka.celestina@dars.si. Visit

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=017615-2018,

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=522697-2017,

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=505444-2017

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=497526-2017.

Ref.n. 000209/2017. 03/18.



Permalink

Postponed from 13.02.2018 to 06.03.2018 the deadline of the open invitation for the construction of the second tube (East tube) of the 8km Karavanke/Karawanken tunnel linking the Slovenian A2 and Austrian A11 motorways. The duration of the contract is 60 months. Deadline for accepting the tenderer's questions: 11.02.2018. Further information from https://www.enarocanje.si/App/Datoteke/239120/Dodatek-4_209-2017-za_objavo.zip. Contact Dars, attn Metka Celestina Cesnovar, Celie, tel +386 13009959, fax+386 13009929, email metka.celestina@dars.si. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=030243-2018. Ref.n. 000209/2017. 04/18.



Permalink

Additional information for the open invitation to tender, deadline 06.03.2018, for the construction of the second tube (East tube) of the 8km Karavanke/Karawanken tunnel linking Slovenian A2 and Austrian A11 motorways. The duration of the contract is 60 months. Further information from https://www.enarocanje.si/App/Datoteke/240436/dodatek_5.zip. Contact Dars, attn Metka Celestina Cesnovar, Celie, tel +386 13009959, fax +386 13009929, email metka.celestina@dars.si. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=043451-2018.

Ref.n. 000209/2017. 03/18.



Permalink

Additional information for the open invitation to tender, deadline 06.03.2018, for the construction of the second tube (East tube) of the 8km Karavanke/Karawanken tunnel linking Slovenian A2 and Austrian A11 motorways. The deadline for accepting the bidder's questions has been postponed from 11.02.2018 to 21.02.2018. Contact Dars, attn Metka Celestina Cesnovar, Celie, tel +386 13009959, fax +386 13009929, email metka.celestina@dars.si. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=060338-2018.

Ref.n. 000209/2017. 07/18.



Permalink

Postponed from 06.03.2018 to 20.03.2018 the deadline of the open invitation for the construction of the second tube (East tube) of the 8km Karavanke/Karawanken tunnel linking the Slovenian A2 and Austrian A11 motorways. The duration of the contract is 60 months. Further information from https://www.enarocanje.si/App/Datoteke/244437/dodatek_8.zip. Contact Dars, attn Metka Celestina Cesnovar, Celie, tel +386 13009959, fax+386 13009929, email metka.celestina@dars.si. Visit http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=075626-2018 and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=091385-2018. Ref.n. 000209/2017. 10/18.



Permalink


Open invitation to tender, deadline 19/07/2022, for the design of the first tube refurbishment of the 8km Karavanke/Karawanken tunnel linking Slovenian A2 and Austrian A11 motorways. The duration of the contract is from 03/10/2022 al 31/12/2028. For bid documents, please click here. Contact Asfinaf, Vienna, tel +43 50108-14447, fax +43 50108-14362, email Marco.Sevim@asfinag.at. Visit  

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=377423-2022 and http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=321831-2022.  Ref. 2022/PROVIA n.80551. 28/22. 

 




Permalink


The Joint Venture IL-Ingenieurbüro Laabmayr & Partner ZT GmbH (Salzburg),  IGT Geotechnik und Tunnelbau ZT GmbH (Salzburg) and  iC Consulenten ZT GmbH (Salzburg) have secured the EUR 1.08 million contract, excluding VAT, for the design of the first tube refurbishment of the 8km Karavanke/Karawanken tunnel linking Slovenian A2 and Austrian A11 motorways. Contact Asfinaf, Vienna, tel +43 50108-14447, fax +43 50108-14362, email Marco.Sevim@asfinag.at. Visit  

http://ted.europa.eu/udl?request=Seek-Deliver&language=en&docid=493164-2022.  Ref. 2022/PROVIA n.80551. 36/22. 



Permalink


Open invitation to tender, deadline 23/04/2024, for E&M equipment in the bitube Karawanken tunnel, motorway A11 (Package 02). Click here for bid/tender documents. Duration of the contract is from 01/08/2024 to 28/11/2028. Contact ASFINAG Bau Management GmbH, attn Eng. Markus Keller, Vienna, tel +43 6646010814565, fax +43 5010814562, email markus.keller@asfinag.at. Visit https://ted.europa.eu/en/notice/-/detail/159761-2024. Ref. Provia n. 114106. 12/24.



Permalink


Open invitation to tender, deadline 23/04/2024, for E&M equipment in the bitube Karawanken tunnel, motorway A11 (Package 02). Click here for bid/tender documents. Duration of the contract is from 01/08/2024 to 28/11/2028. Contact ASFINAG Bau Management GmbH, attn Eng. Markus Keller, Vienna, tel +43 6646010814565, fax +43 5010814562, email markus.keller@asfinag.at. Visit https://ted.europa.eu/en/notice/-/detail/159761-2024. Ref. Provia n. 114106. 12/24.



Permalink