On the 12/06/2020 TBM Maria broke through at the C20 Kondratowicza station. The TBM completed the first part of the right tunnel on the north-east section of metro Line 2 in Warsaw.
The north-eastern extension of the Warsaw metro Line 2 includes three stations: C19 Zacisze, C20 Kondratowicza, and C21 Brodno with holding tracks, three ventilation shafts V19, V20, V21, receiving shaft C18 (KD18) and three single-rail track tunnels D19, D20, D2. The total length of tunnels D19, D20, D21 (without the length of the station) is 5,787 m to be lined with 3858 prefabricated rings please click here to see the TBM in action. Maria will now begin driving a 1320 m tunnel towards the C19 Zacisze station after she completes her maintenance stop.
Anna, the second TBM, has driven just 7 m of the left tunnel (D21) between Brodno and Kondratowicz stations.
The contractor, a consortium of Astaldi and Gülermak, has until September 2021 to complete the project worth PLN 1,397,895000. Completion of the east-north section is part of the project "Construction of the second metro line with the purchase of rolling stock - stage III", which is co-financed by the European Union from the Cohesion Fund under the Operational Program Infrastructure and Environment 2014-2020. For the project with a value of PLN 3,56 536 216.00, EU funding of PLN 1,952,515,513.23 was granted. To learn more please click here and pl/11 for the tunnelbuilder archive. Also visit https://www.metro.waw.pl/ and http://www.um.warszawa.pl. 25/20.