Thai
contractor Nawarat Patanakarn PCL gears up for its second TBM drive on the
Bangkok Metropolitan Electricity Authority’s (MEA) Phra Khanong Cable Tunnel Project.
On September
22, 2017, a TERRATEC Tight Radius Shield successfully completed a technically
challenging tunnel drive for the Bangkok Metropolitan Electricity Authority’s
(MEA) Phra Khanong Cable Tunnel Project, in Bangkok, Thailand. The 3.20m
diameter TERRATEC S48 Earth Pressure Balance Tunnel Boring Machine (EPBM),
which is being operated by Thai contractor Nawarat Patanakarn PCL, was required
to excavate a sharp 32m-radius curve as it exited the project’s launch shaft in
order to negotiate the piles of an adjacent expressway ramp.
To achieve
this challenging curved alignment, the TERRATEC machine was manufactured with
an extreme X-type articulation system that provides a maximum articulation
angle of 6.6-degrees. “The TBM was specifically designed to cope with small
radius curves,” said Mr Pakpong Phongsaisri, Project Engineer for Nawarat
Patanakarn. “It is a highly efficient machine and has done an excellent job
in difficult conditions.”
Designed to
accommodate a new high-voltage cable system, the Phra Khanong Cable Tunnel
Project is the first of a series of planned tunnelling projects by the MEA that
are being built to meet increased power demands in the Thai capital.
Located at
the intersection of the Phra Khanong canal and Sukhumvit Road the project is
situated in one of the busiest areas of downtown Bangkok and is subject to
tight alignment constraints. The TBM was launched on its first, 495m long,
drive in early February from a 7.0m diameter shaft located beneath an elevated
expressway ramp with limited working head room. Due to the presence of the
expressway piles, the TBM was required to embark on a sharp 32m-radius curve
immediately upon exiting the shaft.
Tunnelling
operations were closely observed throughout the manoeuvre via a settlement
monitoring programme that demonstrated minimal impact on the existing above
ground structures. As the machine progressed through the curve it installed a
tunnel lining of short 300mm wide x 125mm thick steel sets, before
transitioning to 1.1m wide x 225mm thick traditional tapered precast concrete
segments (left/right/straight).
Featuring a
classic soft ground open spoke cutterhead design, with knife bits to assist
break-in and break-out of the steel fibre reinforced concrete shaft eyes, the
EPB machine has coped extremely well with the geological conditions along the
alignment, which consist of fine sands and stiff clays with a groundwater head
of about 2 bars.
Prior to the
TBM’s breakthrough last month, the machine completed a second, 30m long
99m-radius, curve on its approach to the reception shaft, which was handled
with ease.
Since then,
the TBM has been retrieved and is currently being prepared for its second,
293m-long, drive from the central launch shaft, which will commence in
mid-November. Once again, the TBM will launch into a tight curve, this time
with a 43.7m-radus on a 2% up-grade trajectory, passing under the Phra Khanong
canal and heading northwards to a second retrieval shaft.
Throughout
the duration of the project, machine operation is being assisted at all times
by TERRATEC’s highly-experienced Field Service team. “We are extremely
pleased with the service and support offered by the Terratec team and are
looking forward to successful completion of the tunnelling works in the coming
months,” says Phongsaisri.
For more
information visit: www.terratec.co