The Gulermak, Nurol & Makyol joint venture conduct TBM
testing on-site for the new Ümraniye Ataşehir-Göztepe Metro line, the latest
addition to Istanbul’s transportation expansion.
TERRATEC is pleased to announce the successful site
acceptance testing of two new 6.56m diameter Earth Pressure Balance Tunnel
Boring Machines (EPBMs) for the ongoing expansion of Istanbul’s Metro system,
in Turkey. These EPBMs, along with another two new sister machines that have
been delivered to this project, will bring the number of TERRATEC machines
working on the city’s metro to a total of seven. The new TBMs will be used by
the Gulermak, Nurol & Makyol JV on the Ümraniye Ataşehir-Göztepe Metro
line, which was awarded in April 2017. The 13km-long line, along with 11 new
stations and NATM-built connections, will form a second north to south rail
corridor under the densely-populated Anatolian side of the city and will be
located entirely underground at an average depth of about 30m.
The robust TERRATEC TBMs have versatile mixed-face
dome-style cutterheads with an opening ratio of about 35% that have proven to
work extremely effectively in Istanbul’s mixed geology – which includes
low-strength sandstones, siltstones, limestones and shales – as well as other state-of-the-art
features such as VFD electric cutterhead drives, tungsten carbide soft ground
cutting tools that are interchangeable with 17’’ roller disc cutters, high
torque screw conveyors and active articulation systems.
These machines (S65 and S66) will be launched from Finans
Merkezi Station and mine towards the Göztepe Station. As the TBMs progress on a
24hr basis, they will install 1,500mm wide by 300mm thick pre-cast concrete
lining rings, which consist of five segments plus a key. Mucking will be via continuous
conveyor with TBM and materials supply provided with the use of Multi-Service
Vehicles (MSVs).
The Ümraniye-Ataşehir-Göztepe project is one of five new
metro lines currently being built by the Istanbul Metropolitan Municipality
(IMM). Members of the JV were so impressed with the performance of the TERRATEC
machine used on the Mecidiyeköy Mahmutbey Metro, which is being built by the
Gulermak, Kolin & Kalyon Joint Venture – and the progress of two other
6.56m diameter EPBMs that were delivered in 2017 to the Şenbay
Madencilik-Kolin-Kalyon Joint Venture for the Dudullu-Bostancı Metro Line –
that they were keen to employ a further four TERRATEC machines on this latest
project.
In March 2018, one the Dudullu-Bostancı TERRATEC EPBMs
completed an outstanding advance of 19 rings in a single shift (equating to
26.5m of excavation in just 12-hours), to accomplish a new production record
for a TBM of this size and class in Istanbul. “Terratec is excited to be
providing yet more machines to the metro projects in Istanbul,” says TERRATEC
Sales & Marketing Director, Bruce Matheson. “We are confident they will
perform as well as previous machines have in the city and we look forward to
breaking more records for on-time delivery, quick assembly and excellent
production rates.” The new lines will increase the city’s current 145km Metro
network to more than 480km.
Watch this video of TERRATEC TBM S65 – On Site Testing in
Istanbul: http://www.terratec.co/video/08.html or
https://youtu.be/PHyq24xXRJg
For more information visit: www.terratec.co
. Media inquiries info@terratec.co / pr@terratec.co