It’s a successful FAT for the TBM - 200 m long, 300 t weight and with a 7.08 m diameter - that will drive the 11.3km Rentvanns/Clear Water tunnel between Trosterud and Huseby for the NVO (Ny Vannforsyning Oslo/New Water Supply for Oslo), contract E6. The TBM will be now dismantled and shipped to Oslo.
The tunnel contract E6 - awarded to the Joint Venture AF Ghella - also includes access tunnels, pumping station and clean water basins at Trosterud and the tunnel section Oset-Disen (3 km) to be blasted; the laying of pipes in the clean water tunnel, and the establishment of a connection to the water distribution network. Click no/85 for tunnelbuilder archive. Visit https://www.oslo.kommune.no, https://www.ghella.com/en and https://afgruppen.no/. 28/23