On the 19.06.2018 TBM
La Carolina reached the end of its underground journey after boring 3.55 km of
tunnel and installing 2,281 concrete rings for the Quito Metro. The TBM began
the excavation works in June 2017, at Solanda station and it reached its first
station, Moran Valverde, in January 2018 after constructing 1.9 km of tunnel,
where it underwent maintenance and upkeep work to continue its final journey to
Quitumbe station.
The three TBMs, involved in the construction of the Quito
Metro line 1, have completed 74% of the tunnelling works, 15.39 km of the total
tunnel construction.
The overall project is 67% complete, with 73 action points
between stations and supplementary works, such as ventilation shafts, emergency
exits, terrain preparation prior to the arrival of the TBMs, and station
accesses. To date, the foundations have been laid at 13 stations, and spaces on
the surface that have been used to build the metro are being gradually returned
to their previous use.
The future line 1 of the Quito Metro, which is being built
by Acciona, who will have 22.6 km of tunnel and 15 stations to finish. Click here and ec/19 for tunnelbuilder archive. Visit http://www.metrodequito.gob.ec. 27/18.