On the 26.12.2018 the Mumbai Metro-3 (Colabata-Bandra-Seepz) Wainganga 2 TBM broke through at the future Seepz station in Andheri.
The TBM was originally launched on the 23.08.2018 from Sariput Nagar shaft, near Aerey Colony, and has now completed its tunnel drive of 568 m and installing 405 rings. The TBM tunnelled 4.5 m daily for 125 days. Nearly 15 km of tunnelling has been completed and all 17 TBMs have started work on 10 different project sites. The total length of the underground corridor is 33.5 km; it will connect the island city with western suburbs. To read in detail about the breakthrough please click this link https://www.mmrcl.com/sites/default/files/Press%20Release%20-%202nd%20Tunnel%20Break%20Through.pdf. For further information please click here for the video of the breakthrough, and for the tunnelbuilder archive click here and in/77. More can be found at https://www.mmrcl.com/en . 52/18.
16.05.2025 Italy
16.05.2025 Switzerland
22.05.2025 Austria
23.05.2025 Switzerland
26.05.2025 Czech Republic
26.05.2025 Norway
28.05.2025 Italy
30.05.2025 Poland
02.06.2025 Spain
04.06.2025 Norway
04.06.2025 Austria
05.06.2025 Iceland
09.06.2025 Switzerland
16.06.2025 Spain
17.06.2025 Italy
17.06.2025 France
19.06.2025 France
19.06.2025 Italy
24.06.2025 Switzerland
27.06.2025 Switzerland
28.07.2025 Brazil