On the 24.09.2018 the TBM Wainganga completed its first tunnel for the 33.5-km Colaba-Bandra-Seepz (Metro-3 line). The 1.26-km tunnel between Pali ground in Marol, Andheri (East) and the International airport terminal T2 was completed in 259 days with an average speed of 4.6m/day.
The tunnel is part of the 4.15 km Terminal T2 - Aarey section whose construction was awarded to the Joint Venture between L&T-STEC (Package07). The TBM, launched in Marol on 08.01.2018, and drove through rocky strata made of basalt, breccia and tuff and completed excavation near Terminal T2. Click here and in/77 for the tunnelbuilder archive. Visit https://www.mmrcl.com/en. 40/18.
30.03.2026 Italy
31.03.2026 Ireland
07.04.2026 Austria
08.04.2026 Norway
09.04.2026 France
09.04.2026 Germany
14.04.2026 United States
23.04.2026 Sweden
24.04.2026 United Kingdom
24.04.2026 Switzerland
27.04.2026 Italy
27.04.2026 Switzerland
30.04.2026 Sweden
30.04.2026 Switzerland
04.05.2026 Switzerland
04.05.2026 Slovakia
04.06.2026 Switzerland
07.07.2026 Germany
31.12.2031 Germany