SELI Overseas is the first to complete the TBM excavation on the Gold Line in Doha. On Sunday 01/05/16 at approximately 10.00am TBM 6 will broke through into the Al Aziziyah Station in Doha. TBM 6 is the first one, out of the 6 Herrencknecht TBMs that are excavating the Doha Gold Line Metro, to have completed its 4,5 km long drive. SELI Overseas, executed this section in subcontractor to ALYSJ JV, and was actually the last to start tunnelling but the first to complete its drive. SELI Overseas as part of this project has broken the world production records for an EPB TBM with 920 m of tunnel excavated to the highest standards in just 1 month. The breakthrough was achieved 2 months ahead of the original programme despite an initial delay of about 2 months with the assembly of the TBM.
All together SELI Overseas completed the drive after only 1 year from the signature of the subcontract. This is a fantastic achievement never done before by anyone on a metro project. Click here for tunnelbuilder archive. Visit http://www.selioverseas.com/. 18/16.
30.04.2024 Germany
07.05.2024 Poland
07.05.2024 Switzerland
13.05.2024 India
15.05.2024 Czech Republic
15.05.2024 Macedonia
16.05.2024 Finland
17.05.2024 Finland
24.05.2024 Switzerland
31.05.2024 Switzerland
07.06.2024 Canada
15.12.2024 Austria