SELI Overseas is the first to complete the TBM excavation on the Gold Line in Doha. On Sunday 01/05/16 at approximately 10.00am TBM 6 will broke through into the Al Aziziyah Station in Doha. TBM 6 is the first one, out of the 6 Herrencknecht TBMs that are excavating the Doha Gold Line Metro, to have completed its 4,5 km long drive. SELI Overseas, executed this section in subcontractor to ALYSJ JV, and was actually the last to start tunnelling but the first to complete its drive. SELI Overseas as part of this project has broken the world production records for an EPB TBM with 920 m of tunnel excavated to the highest standards in just 1 month. The breakthrough was achieved 2 months ahead of the original programme despite an initial delay of about 2 months with the assembly of the TBM.
All together SELI Overseas completed the drive after only 1 year from the signature of the subcontract. This is a fantastic achievement never done before by anyone on a metro project. Click here for tunnelbuilder archive. Visit http://www.selioverseas.com/. 18/16.
04.02.2026 Germany
06.02.2026 Spain
09.02.2026 Norway
16.02.2026 Iceland
17.02.2026 France
19.02.2026 Sweden
23.02.2026 Switzerland
19.03.2026 Bulgaria
24.03.2026 Italy
23.04.2026 Sweden
24.04.2026 United Kingdom