At Watson Island, on 15.04.2013, the TBM Harriet completed excavation of the second of two underwater tunnels as part of the EUR770 million project connecting the Port of Miami with nearby expressways. The EUR35 million TBM began its first drive at Watson Island, off downtown Miami, in November, 2011. It reached the port on 31.07.2012. It was then disassembled, turned around and reassembled for a return trip starting 29.10.2012. Paving is presently underway inside the tunnel. When completed in May, 2014, the tunnel will afford a direct route for freight to the port from nearby expressways such as Interstate 95, avoiding congested downtown streets. Click us/43 for tunnelbuilder archive. Visit http://www.portofmiamitunnel.com/. 20/13.
12.01.2026 Austria
14.01.2026 Netherlands
15.01.2026 Spain
16.01.2026 Germany
20.01.2026 Romania
23.01.2026 Switzerland
23.01.2026 Ireland
26.01.2026 Italy
26.01.2026 Germany
29.01.2026 Bosnia and Herzegovina
04.02.2026 Germany
06.02.2026 Spain
09.02.2026 Norway