Almost 2/3 of the Follo line tunnel has now been completed by, the
joint venture between Ghella and Acciona. They have bored 24,000 m through
extremely hard rock which has been interspersed with weak zones. Eufemia, the first TBM, started in
September 2016. Altogether the four TBMs have approximately excavated around
66% of the total length. The first breakthrough in the northern direction is
expected at the end of this Summer in 2018.
The TBM Eufemia has excavated almost 7 km, 77 % of her way
to Oslo, and Ellisiv is following only 60 ms behind. They are both ahead of
schedule. The average progress is 100 m/week per machine. The TBMs Anna and
Magda are working continuously towards Ski, and they are also on schedule. They
have excavated respectively 5.2 km (57 %) and 5 km (55 %).
The precast factory has produced approximately 15 400 tunnel
rings, around 75% of the 20,236 total needed. AGJV is constructing the main
part of the tunnel on the project on behalf of Bane NOR. Click no/86 for
tunnelbuilder archive. Visit http://agjv.no.
14/18.